All Heads of Government Implementing
Agencies, Including Government-Owned or
Controlled Corporations or Authorities
SUBJECT : Requiring all Government Implementing Agencies including Government-owned or
controlled corporations and authorities, to fully cooperate and participate in the
Post-Evaluation of Major Development Projects
WHEREAS, the country's development programs for the coming years call for substantial expansion of the public investment program;
WHEREAS, the relative scarcity of investable resources stresses the need for continuing efforts to ensure that projects to be carried out are well-designed, appropriately reviewed and selected, and effectively executed;
WHEREAS, the process of post-project evaluation constitutes one of the means by which improvements in project development can be effected;
NOW, THEREFORE, I, FERDINAND E. MARCOS, President of the Philippines, by virtue of the powers vested in me by the Constitution, do hereby order and authorize:
The institutionalization of a post-evaluation system through which concerned government agencies, by conducting a review and assessment of project performance shortly after completion of implementation/construction and/or during the operational stage can draw lessons that may fruitfully be applied to current and/or future project preparation and implementation work. Under this system:
A)
All government implementing line agencies, including government-owned
and controlled corporations and authorities, are required to prepare
Project Completion Reports (PCR's) in collaboration with the National
Economic and Development Authority (NEDA), six months to one year after
completion of implementation of major development projects. For this
purpose, the NEDA shall determine those projects that are to be
considered as "major" for each project category and advise the
concerned agencies accordingly;
B) Upon completion of the aforesaid PCR's, all
government implementing line agencies, including government-owned or
controlled corporations and authorities, shall transmit them to the
NEDA for evaluation. Based on these PCR's and such other investigations
that it may conduct independently, the NEDA shall prepare Project
Performance Assessment Reports (PPARs) which shall be forwarded to the
NEDA Board through the Director-General, for whatever action is deemed
appropriate; and
C) For major
projects that have been in operation for at least 5 years,
Mid-Operation Reports (MORs) shall be prepared by all government-owned
or controlled corporations and authorities, in collaboration with the
NEDA. The MOR for each major project shall be forwarded to the NEDA for
evaluation, on the basis of which is Mid-Operation Assessment Report
(MOAR) shall be prepared by the NEDA. The MOAR shall similarly be
transmitted to the NEDA Board, through the Director-General, for
whatever action is deemed appropriate.
This Letter of Instruction shall take effect immediately.