10 C.F.R. § 50.23 Construction permits.
Title 10 - Energy
A construction permit for the construction of a production or utilization facility will be issued prior to the issuance of a license if the application is otherwise acceptable, and will be converted upon due completion of the facility and Commission action into a license as provided in §50.56 of this part. A construction permit for the alteration of a production or utilization facility will be issued prior to the issuance of an amendment of a license, if the application for amendment is otherwise acceptable, as provided in §50.91. [21 FR 355, June 19, 1956, as amended at 35 FR 11461, July 17, 1970]
Title 10: Energy
PART 50—DOMESTIC LICENSING OF PRODUCTION AND UTILIZATION FACILITIES
Classification and Description of Licenses
§ 50.23 Construction permits.