10 C.F.R. § 75.6 Maintenance of records and delivery of information, reports, and other communications.
Title 10 - Energy
(a) All information and reports required to be submitted pursuant to the provisions of this part and other communications concerning the regulations in this part shall be delivered as follows: (b) If an installation is a nuclear power plant or a non-power reactor for which a construction permit or operating license has been issued, whether or not a license to receive and possess nuclear material at the installation has been issued, the cognizant Director is the Director, Office of Nuclear Reactor Regulation. For all other installations, the cognizant Director is the Director, Office of Nuclear Material Safety and Safeguards. (c) Except where otherwise specified, all communications and reports concerning the regulations in this part and applications filed under them should be sent by mail addressed: ATTN: Document Control Desk; Director, Office of Nuclear Reactor Regulation (or Director, Nuclear Materials Safety and Safeguards, as appropriate), U.S. Nuclear Regulatory Commission, Washington, DC 20555–0001; by hand delivery to the NRC's offices at 11555 Rockville Pike, Rockville, Maryland; or, where practicable, by electronic submission, for example, via Electronic Information Exchange, or CD-ROM. Electronic submissions must be made in a manner that enables the NRC to receive, read, authenticate, distribute, and archive the submission, and process and retrieve it a single page at a time. Detailed guidance on making electronic submissions can be obtained by visiting the NRC's Web site at http://www.nrc.gov/site-help/eie.php, by calling (301) 415–6030, by e-mail to [email protected], or by writing the Office of Information Services, U.S. Nuclear Regulatory Commission, Washington, DC 20555–0001. The guidance discusses, among other topics, the formats the NRC can accept, the use of electronic signatures, and the treatment of nonpublic information. (d) Communications to the Regional Office of the NRC shall be addressed to the office listed in Appendix A of part 73 of this chapter for the region in which the installation is located. (e) Each record required by this part must be legible throughout the retention period specified by each Commission regulation. The record may be the original or a reproduced copy or a microform provided that the copy or microform is authenticated by authorized personnel and that the microform is capable of producing a clear copy throughout the required retention period. The record may also be stored in electronic media with the capability for producing legible, accurate, and complete records during the required retention period. Records such as letters, drawings, specifications, must include all pertinent information such as stamps, initials, and signatures. The licensee shall maintain adequate safeguards against tampering with and loss of records. [45 FR 50711, July 31, 1980, as amended at 52 FR 31613, Aug. 21, 1987; 53 FR 6139, Mar. 1, 1988; 53 FR 19262, May 27, 1988; 53 FR 43422, Oct. 27, 1988; 68 FR 58822, Oct. 10, 2003]
Title 10: Energy
PART 75—SAFEGUARDS ON NUCLEAR MATERIAL—IMPLEMENTATION OF US/IAEA AGREEMENT
General Provisions
§ 75.6 Maintenance of records and delivery of information, reports, and other communications.
------------------------------------------------------------------------ Item Section Manner of deliver------------------------------------------------------------------------IAEA Representative................. 75.7 To the Cognizant Director.Facility Attachments................ 75.8 Do.Installation Information............ 75.11 Do.Sensitive Information............... 75.12 Do.Verification of Installation 75.13 Do. Information.Supplemental Information............ 75.14 Do.General Requirements (Amplification) 75.31 As specified in the request.Initial Inventory Report............ 75.32 In accordance with printed instructions for preparation of DOE/NRC Form-742.Inventory Change Reports............ 75.34 In accordance with printed instructions for preparation of DOE/NRC Form-741, and -740M.Material Status Reports............. 75.35 In accordance with printed instructions for preparation of DOE/NRC Form-742, - 742C, and -740M.Special Reports..................... 75.36 To the Regional Office of the NRC.Inspection.......................... 75.42 Do.Transfers (advance notification).... 75.43 Do.Delays.............................. 75.44 Do.Other Communications................ .......... To the cognizant Director.------------------------------------------------------------------------