Title 10 - Energy
If the application references an early site permit or a certified standard design, the environmental review must focus on whether the design of the facility falls within the parameters specified in the early site permit and any other significant environmental issue not considered in any previous proceeding on the site or the design. If the application does not reference an early site permit or a certified standard design, the environmental review procedures set out in 10 CFR part 51 must be followed, including the issuance of a final environmental impact statement, but excluding the issuance of a supplement under §51.95(a).