10 C.F.R. § 52.103   Operation under a combined license.


Title 10 - Energy


Title 10: Energy
PART 52—EARLY SITE PERMITS; STANDARD DESIGN CERTIFICATIONS; AND COMBINED LICENSES FOR NUCLEAR POWER PLANTS
Subpart C—Combined Licenses

Browse Previous

§ 52.103   Operation under a combined license.

(a) Not less than one hundred and eighty days before the date scheduled for initial loading of fuel into a plant by a licensee that has been issued a combined construction permit and operating license under subpart C of this part, the Commission shall publish in the Federal Register notice of intended operation. That notice shall provide that any person whose interest may be affected by operation of the plant, may within sixty days request the Commission to hold a hearing on whether the facility as constructed complies, or on completion will comply, with the acceptance criteria of the license.

(b) A request for hearing under paragraph (a) of this section shall show, prima facie, that—

(1) One or more of the acceptance criteria in the combined license have not been, or will not be met; and

(2) The specific operational consequences of nonconformance that would be contrary to providing reasonable assurance of adequate protection of the public health and safety.

(c) After receiving a request for a hearing, the Commission expeditiously shall either deny or grant the request. If the request is granted, the Commission shall determine, after considering petitioners' prima facie showing and any answers thereto, whether during a period of interim operation, there will be reasonable assurance of adequate protection of the public health and safety. If the Commission determines that there is such reasonable assurance, it shall allow operation during an interim period under the combined license.

(d) The Commission, in its discretion, shall determine appropriate hearing procedures, whether informal or formal adjudicatory, for any hearing under paragraph (a) of this section, and shall state its reasons therefor.

(e) The Commission shall, to the maximum possible extent, render a decision on issues raised by the hearing request within one hundred and eighty days of the publication of the notice provided by paragraph (a) of this section or the anticipated date for initial loading of fuel into the reactor, whichever is later.

(f) A petition to modify the terms and conditions of the combined license will be processed as a request for action in accord with 10 CFR 2.206. The petitioner shall file the petition with the Secretary of the Commission. Before the licensed activity allegedly affected by the petition (fuel loading, low power testing, etc.) commences, the Commission shall determine whether any immediate action is required. If the petition is granted, then an appropriate order will be issued. Fuel loading and operation under the combined license will not be affected by the granting of the petition unless the order is made immediately effective.

(g) Prior to operation of the facility, the Commission shall find that the acceptance criteria in the combined license are met. If the combined license is for a modular design, each reactor module may require a separate finding as construction proceeds.

[57 FR 60978, Dec. 23, 1992]

Browse Previous








































































chanrobles.com





ChanRobles Legal Resources:

ChanRobles On-Line Bar Review

ChanRobles Internet Bar Review : www.chanroblesbar.com

ChanRobles MCLE On-line

ChanRobles Lawnet Inc. - ChanRobles MCLE On-line : www.chanroblesmcleonline.com