10 C.F.R. § 205.321 Time of filing.
Title 10 - Energy
Pursuant to the DOE's responsibility under the National Environmental Policy Act, the DOE must make an environmental determination of the proposed action. If, as a result of this determination, an environmental impact statement (EIS) must be prepared, the permit processing time normally will be 18–24 months. If no environmental impact statement is required, then a six-month processing time normally would be sufficient.
Title 10: Energy
PART 205—ADMINISTRATIVE PROCEDURES AND SANCTIONS
Subpart W—Electric Power System Permits and Reports; Applications; Administrative Procedures and Sanctions
Application for Presidential Permit Authorizing the Construction, Connection, Operation, and Maintenance of Facilities for Transmission of Electric Energy at International Boundaries
§ 205.321 Time of filing.