10 C.F.R. Subpart B—Reimbursement Criteria


Title 10 - Energy


Title 10: Energy
PART 765—REIMBURSEMENT FOR COSTS OF REMEDIAL ACTION AT ACTIVE URANIUM AND THORIUM PROCESSING SITES

Browse Previous |  Browse Next

Subpart B—Reimbursement Criteria

§ 765.10   Eligibility for reimbursement.

(a) Any licensee of an active uranium or thorium processing site that has incurred costs of remedial action for the site that are attributable to byproduct material generated as an incident of sales to the United States shall be eligible for reimbursement of these costs, subject to the procedures and limitations specified in this part.

(b) Prior to reimbursement of costs of remedial action incurred by a licensee, the Department shall make a determination regarding the total quantity of dry short tons of byproduct material, and the quantity of Federal-related dry short tons of byproduct material present on October 24, 1992 at the licensee's active processing site. A claim for reimbursement from a site for which a determination is made will be evaluated individually. If a licensee does not concur with the Department's determination regarding the quantity of dry short tons of byproduct material present at the site, the licensee may appeal the Department's determination in accordance with §765.22 of this part. The Department's determination shall be used to determine that portion of an approved claim for reimbursement submitted by the licensee which shall be reimbursed, unless or until the determination is overturned on appeal. If the outcome of an appeal requires a change in the Department's initial determination, the Department will adjust any payment previously made to the licensee to reflect the change.

§ 765.11   Reimbursable costs.

(a) Costs for which a licensee may be reimbursed must be for remedial action that a licensee demonstrates is attributable to byproduct material generated as an incident of sales to the United States, as determined by the Department. These costs are equal to the total costs of remedial action at a site multiplied by the Federal reimbursement ratio established for the site. These costs must be incurred in the performance of activities, prior to or after enactment of UMTRCA, and required by a plan, portion thereof, or other written authorization, approved by NRC or by an Agreement State. Costs of remedial action shall be reimbursable only if approved by the Department in accordance with the provisions of this part.

(b) In addition, costs of remedial action incurred by a licensee after December 31, 2007 must be in accordance with a plan for subsequent remedial action approved by the Department as specified in §765.30.

(c) Total reimbursement of costs of remedial action incurred at an active processing site that are otherwise reimbursable pursuant to the provisions of this part shall be limited as follows:

(1) Reimbursement of costs of remedial action to active uranium processing site licensees shall not exceed $6.25, as adjusted for inflation, multiplied by the number of Federal-related dry short tons of byproduct material.

(2) Aggregate reimbursement of costs of remedial action incurred at all active uranium processing sites shall not exceed $350 million. This aggregate amount shall be adjusted for inflation pursuant to §765.12; and

(3) Reimbursement of costs of remedial action at the active thorium processing site shall be limited to costs incurred for offsite disposal and shall not exceed $365 million. This amount shall be adjusted for inflation pursuant to §765.12.

(d) Notwithstanding the Title X requirement that byproduct material must be located at an active processing site on October 24, 1992, byproduct material moved from the Edgemont Mill in Edgemont, South Dakota, to a disposal site as a result of remedial action, shall be eligible for reimbursement in accordance with all applicable requirements of this part.

[59 FR 26726, May 23, 1994, as amended at 68 FR 32957, June 3, 2003]

§ 765.12   Inflation index adjustment procedures.

(a) The amounts of $6.25 (as specified in §765.2(e) of this rule) $350 million (as specified in §765.2(f) of this rule), $365 million (as specified in §765.2(g) of this rule) and $715 million (as specified in §765.2(i) of this rule) shall be adjusted for inflation as provided by this section.

(b) To make adjustments for inflation to the amounts specified in paragraph (a) of this section, the Department shall apply the CPI-U to these amounts annually, beginning in 1994, using the CPI-U as published by the Bureau of Labor Statistics within the Department of Commerce for the preceding calendar year.

(c) The Department shall adjust annually, using the CPI-U as defined in this part, amounts paid to an active uranium processing site licensee for purposes of comparison with the $6.25 per dry short ton limit on reimbursement as adjusted for inflation.

[59 FR 26726, May 23, 1994, as amended at 68 FR 32957, June 3, 2003]

Browse Previous |  Browse Next









































































chanrobles.com





ChanRobles Legal Resources:

ChanRobles On-Line Bar Review

ChanRobles Internet Bar Review : www.chanroblesbar.com

ChanRobles MCLE On-line

ChanRobles Lawnet Inc. - ChanRobles MCLE On-line : www.chanroblesmcleonline.com