10 C.F.R. § 950.24   Claims determination for covered costs.


Title 10 - Energy


Title 10: Energy
PART 950—STANDBY SUPPORT FOR CERTAIN NUCLEAR PLANT DELAYS
Subpart C—Claims Administration Process

Browse Previous |  Browse Next

§ 950.24   Claims determination for covered costs.

(a) No later than thirty (30) days from the sponsor's submission of a Certification of Covered Costs, the Claims Administrator shall issue a Claim Determination identifying those claimed costs deemed to be reasonable and appropriate based on an evaluation of:

(1) The duration of covered delay, taking into account contributory or concurrent delays resulting from events excluded from coverage;

(2) The covered costs associated with covered delay, including an assessment of the sponsor's due diligence in mitigating or ending covered costs, as set forth in §950.23;

(3) Any adjustments to the covered costs, as set forth in §950.26; and

(4) Other information as necessary and appropriate.

(b) The Claim Determination shall state the Claims Administrator's determination that the claim shall be paid in full, paid in an adjusted amount as deemed appropriate by the Claims Administrator, or rejected in full.

(c) Should the Claims Administrator conclude that the sponsor has not supplied the required information in the Certification of Covered Costs or any supporting documentation sufficient to allow reasonable verification of the duration of the covered delay or covered costs, the Claims Administrator shall so inform the sponsor and specify the nature of additional documentation requested, in time for the sponsor to supply supplemental documentation and for the Claims Administrator to issue the Claim Determination.

(d) Should the Claims Administrator find that any claimed covered costs are not appropriate or otherwise should be considered excluded costs under the Standby Support Contract, the Claims Administrator shall identify such costs and state the reason(s) for that decision in writing. If the parties cannot agree on the covered costs, they shall resolve the dispute in accordance with the requirements in subpart D of this part.

Browse Previous |  Browse Next























































chanrobles.com





ChanRobles Legal Resources:

ChanRobles On-Line Bar Review

ChanRobles Internet Bar Review : www.chanroblesbar.com

ChanRobles MCLE On-line

ChanRobles Lawnet Inc. - ChanRobles MCLE On-line : www.chanroblesmcleonline.com