15 C.F.R. Subpart D—Industrial Priorities


Title 15 - Commerce and Foreign Trade


Title 15: Commerce and Foreign Trade
PART 700—DEFENSE PRIORITIES AND ALLOCATIONS SYSTEM

Browse Previous |  Browse Next

Subpart D—Industrial Priorities

§ 700.10   Delegation of authority.

(a) The priorities and allocations authorities of the President under Title I of the Defense Production Act with respect to industrial resources have been delegated to the Secretary of Commerce under Executive Order 12919 of June 3, 1994 (59 FR 29525). The priorities authorities of the President under the Selective Service Act and related statutes with respect to industrial resources have also been delegated to the Secretary of Commerce under Executive Order 12742 of January 8, 1991 (56 FR 1079).

(b) Within the Department of Commerce, these responsibilities have been assigned to the Office of Strategic Industries and Economic Security. The Department of Commerce has authorized the Delegate Agencies to assign priority ratings to orders for items needed for approved programs.

[49 FR 30414, July 30, 1984. Redesignated at 54 FR 601, Jan. 9, 1989, as amended at 63 FR 31922, June 11, 1998; 71 FR 39528, July 13, 2006]

§ 700.11   Priority ratings.

(a) Levels of priority. (1) There are two levels of priority established by this regulation, identified by the rating symbols “DO” and “DX”.

(2) All DO rated orders have equal priority with each other and take preference over unrated orders. All DX rated orders have equal priority with each other and take preference over DO rated orders and unrated orders. (For resolution of conflicts among rated orders of equal priority, see §700.14(c).)

(3) In addition, a Directive issued by Commerce takes preference over any DX rated order, DO rated order, or unrated order, as stipulated in the Directive. (For a full discussion of Directives, see §700.62.)

(b) Program identification symbols. Program identification symbols indicate which approved program is being supported by a rated order. The list of approved programs and their identification symbols are listed in Schedule I. For example, A1 identifies defense aircraft programs and A7 signifies defense electronic programs. Program identification symbols, in themselves, do not connote any priority.

(c) Priority ratings. A priority rating consists of the rating symbol—DO and DX—and the program identification symbol, such as A1, C2, or N1. Thus, a contract for the production of an aircraft will contain a DO-A1 or DX-A1 priority rating. A contract for a radar set will contain a DO-A7 or DX-A7 priority rating.

[49 FR 30414, July 30, 1984. Redesignated at 54 FR 601, Jan. 9, 1989, as amended at 63 FR 31922, June 11, 1998; 71 FR 39528, July 13, 2006]

§ 700.12   Elements of a rated order.

Each rated order must include:

(a) The appropriate priority rating (e.g. DO-A1, DX-A4, DO-H1);

(b) A required delivery date or dates. The words “immediately” or “as soon as possible” do not constitute a delivery date. A “requirements contract”, “basic ordering agreement”, “prime vendor contract”, or similar procurement document bearing a priority rating may contain no specific delivery date or dates and may provide for the furnishing of items from time-to-time or within a stated period against specific purchase orders, such as “calls”, “requisitions”, and “delivery orders”. These purchase orders must specify a required delivery date or dates and are to be considered as rated as of the date of their receipt by the supplier and not as of the date of the original procurement document;

(c) The written signature on a manually placed order, or the digital signature or name on an electronically placed order, of an individual authorized to sign rated orders for the person placing the order. The signature or use of the name certifies that the rated order is authorized under this part and that the requirements of this part are being followed; and

(d) A statement that reads in substance:

This is a rated order certified for national defense use, and you are required to follow all the provisions of the Defense Priorities and Allocations System regulation (15 CFR part 700).

[49 FR 30414, July 30, 1984. Redesignated at 54 FR 601, Jan. 9, 1989, as amended at 63 FR 31922, June 11, 1998]

§ 700.13   Acceptance and rejection of rated orders.

(a) Mandatory acceptance. (1) Except as otherwise specified in this section, a person shall accept every rated order received and must fill such orders regardless of any other rated or unrated orders that have been accepted.

(2) A person shall not discriminate against rated orders in any manner such as by charging higher prices or by imposing different terms and conditions than for comparable unrated orders.

(b) Mandatory rejection. Unless otherwise directed by Commerce:

(1) A person shall not accept a rated order for delivery on a specific date if unable to fill the order by that date. However, the person must inform the customer of the earliest date on which delivery can be made and offer to accept the order on the basis of that date. Scheduling conflicts with previously accepted lower rated or unrated orders are not sufficient reason for rejection under this section.

(2) A person shall not accept a DO rated order for delivery on a date which would interfere with delivery of any previously accepted DO or DX rated orders. However, the person must offer to accept the order based on the earliest delivery date otherwise possible.

(3) A person shall not accept a DX rated order for delivery on a date which would interfere with delivery of any previously accepted DX rated orders, but must offer to accept the order based on the earliest delivery date otherwise possible.

(4) If a person is unable to fill all the rated orders of equal priority status received on the same day, the person must accept, based upon the earliest delivery dates, only those orders which can be filled, and reject the other orders. For example, a person must accept order A requiring delivery on December 15 before accepting order B requiring delivery on December 31. However, the person must offer to accept the rejected orders based on the earliest delivery dates otherwise possible.

(c) Optional rejection. Unless otherwise directed by Commerce, rated orders may be rejected in any of the following cases as long as a supplier does not discriminate among customers:

(1) If the person placing the order is unwilling or unable to meet regularly established terms of sale or payment;

(2) If the order is for an item not supplied or for a service not performed;

(3) If the order is for an item produced, acquired, or provided only for the supplier's own use for which no orders have been filled for two years prior to the date of receipt of the rated order. If, however, a supplier has sold some of these items, the supplier is obligated to accept rated orders up to that quantity or portion of production, whichever is greater, sold within the past two years;

(4) If the person placing the rated order, other than the U.S. Government, makes the item or performs the service being ordered;

(5) If acceptance of a rated order or performance against a rated order would violate any other regulation, official action, or order of the Department of Commerce issued under the authority of the Defense Production Act or the Selective Service Act and related statutes [See §700.75].

(d) Customer notification requirements. (1) A person must accept or reject a rated order and transmit the acceptance or rejection in writing (hard copy), or in electronic format, within fifteen (15) working days after receipt of a DO rated order and within ten (10) working days after receipt of a DX rated order. If the order is rejected, the person must also provide the reasons for the rejection, pursuant to paragraphs (b) and (c) of this section, in writing (hard copy) or electronic format.

(2) If a person has accepted a rated order and subsequently finds that shipment or performance will be delayed, the person must notify the customer immediately, give the reasons for the delay, and advise of a new shipment or performance date. If notification is given verbally, written or electronic confirmation must be provided within five (5) working days.

(The information collection requirements in paragraphs (d)(1) and (d)(2) are approved by the Office of Management and Budget under OMB control number 0694–0053)

[49 FR 30414, July 30, 1984. Redesignated at 54 FR 601, Jan. 9, 1989, as amended at 63 FR 31922, June 11, 1998; 70 FR 10864, Mar. 7, 2005]

§ 700.14   Preferential scheduling.

(a) A person must schedule operations, including the acquisition of all needed production items, in a timely manner to satisfy the delivery requirements of each rated order. Modifying production or delivery schedules is necessary only when required delivery dates for rated orders cannot otherwise be met.

(b) DO rated orders must be given production preference over unrated orders, if necessary to meet required delivery dates, even if this requires the diversion of items being processed or ready for delivery against unrated orders. Similarly, DX rated orders must be given preference over DO rated orders and unrated orders.

Examples:  If a person receives a DO rated order with a delivery date of June 3 and if meeting that date would mean delaying production or delivery of an item for an unrated order, the unrated order must be delayed. If a DX rated order is received calling for delivery on July 15 and a person has a DO rated order requiring delivery on June 2 and operations can be scheduled to meet both deliveries, there is no need to alter production schedules to give any additional preference to the DX rated order.

(c) Conflicting rated orders. (1) If a person finds that delivery or performance against any accepted rated orders conflicts with the delivery or performance against other accepted rated orders of equal priority status, the person shall give preference to the conflicting orders in the sequence in which they are to be delivered or performed (not to the receipt dates). If the conflicting rated orders are scheduled to be delivered or performed on the same day, the person shall give preference to those orders which have the earliest receipt dates.

(2) If a person is unable to resolve rated order delivery or performance conflicts under this section, the person should promptly seek special priorities assistance as provided in §§700.50 through 700.54. If the person's customer objects to the rescheduling of delivery or performance of a rated order, the customer should promptly seek special priorities assistance as provided in §§700.50 through 700.54. For any rated order against which delivery or performance will be delayed, the person must notify the customer as provided in §700.13(d)(2).

(d) If a person is unable to purchase needed production items in time to fill a rated order by its required delivery date, the person must fill the rated order by using inventoried production items. A person who uses inventoried items to fill a rated order may replace those items with the use of a rated order as provided in §700.17(b).

[49 FR 30414, July 30, 1984. Redesignated at 54 FR 601, Jan. 9, 1989, as amended at 63 FR 31922, June 11, 1998]

§ 700.15   Extension of priority ratings.

(a) A person must use rated orders with suppliers to obtain items needed to fill a rated order. The person must use the priority rating indicated on the customer's rated order, except as otherwise provided in this regulation or as directed by the Department of Commerce.

For example, if a person is in receipt of a DO-A3 rated order for a navigation system and needs to purchase semiconductors for its manufacture, that person must use a DO-A3 rated order to obtain the needed semiconductors.

(b) The priority rating must be included on each successive order placed to obtain items needed to fill a customer's rated order. This continues from contractor to subcontractor to supplier throughout the entire procurement chain.

§ 700.16   Changes or cancellations of priority ratings and rated orders.

(a) The priority rating on a rated order may be changed or cancelled by:

(1) An official action of the Department of Commerce; or

(2) Written notification from the person who placed the rated order (including a Delegate Agency).

(b) If an unrated order is amended so as to make it a rated order, or a DO, rating is changed to a DX rating, the supplier must give the appropriate preferential treatment to the order as of the date the change is received by the supplier.

(c) An amendment to a rated order that significantly alters a supplier's original production or delivery schedule shall constitute a new rated order as of the date of its receipt. The supplier must accept or reject the amended order according to the provisions of §700.13.

(d) The following amendments do not constitute a new rated order: a change in shipping destination; a reduction in the total amount of the order; an increase in the total amount of the order which has negligible impact upon deliveries; a minor variation in size or design; or a change which is agreed upon between the supplier and the customer.

(e) If a person no longer needs items to fill a rated order, any rated orders placed with suppliers for the items, or the priority rating on those orders, must be cancelled.

(f) When a priority rating is added to an unrated order, or is changed or cancelled, all suppliers must be promptly notified in writing.

§ 700.17   Use of rated orders.

(a) A person must use rated orders to obtain:

(1) Items which will be physically incorporated into other items to fill rated orders, including that portion of such items normally consumed, or converted into scrap or by-products, in the course of processing;

(2) Containers or other packaging materials required to make delivery of the finished items against rated orders;

(3) Services, other than contracts of employment, needed to fill rated orders; and

(4) MRO needed to produce the finished items to fill rated orders. However, for MRO, the priority rating used must contain the program identification symbol H7 along with the rating symbol contained on the customer's rated order. For example, a person in receipt of a DO-A3 rated order, who needs MRO, would place a DO-H7 rated order with the person's supplier.

(b) A person may use a rated order to replace inventoried items (including finished items) if such items were used to fill rated orders, as follows:

(1) The order must be placed within 90 days of the date of use of the inventory.

(2) A DO rating symbol and the program identification symbol indicated on the customer's rated order must be used on the order. A DX rating symbol may not be used even if the inventory was used to fill a DX rated order.

(3) If the priority ratings on rated orders from one customer or several customers contain different program identification symbols, the rated orders may be combined. In this case, the program identification symbol H1 must be used (i.e., DO-H1).

(c) A person may combine DX and DO rated orders from one customer or several customers if the items covered by each level of priority are identified separately and clearly. If different program identification symbols are indicated on those rated orders of equal priority, the person must use the program identification symbol H1 (i.e., DO-H1 or DX-H1).

(d) Combining rated and unrated orders. (1) A person may combine rated and unrated order quantities on one purchase order provided that:

(i) The rated quantities are separately and clearly identified; and

(ii) The four elements of a rated order, as required by §700.12, are included on the order with the statement required in §700.12(d) modified to read in substance:

This purchase order contains rated order quantities certified for national defense use, and you are required to follow all the provisions of the Defense Priorities and Allocations System regulation (15 CFR part 700) only as it pertains to the rated quantities.

(2) A supplier must accept or reject the rated portion of the purchase order as provided in §700.13 and give preferential treatment only to the rated quantities as required by this part. This part may not be used to give preferential treatment to the unrated portion of the order.

(3) Any supplier who believes that rated and unrated orders are being combined in a manner contrary to the intent of this regulation or in a fashion that causes undue or exceptional hardship may submit a request for adjustment or exception under §700.80.

(e) A person may place a rated order for the minimum commercially procurable quantity even if the quantity needed to fill a rated order is less than that minimum. However, a person must combine rated orders as provided in paragraph (c) of this section, if possible, to obtain minimum procurable quantities.

(f) A person is not required to place a priority rating on an order for less than $50,000, or one half of the Federal Acquisition Regulation (FAR) Simplified Acquisition Threshold (see FAR 2.101), whichever amount is larger, provided that delivery can be obtained in a timely fashion without the use of the priority rating.

[49 FR 30414, July 30, 1984. Redesignated at 54 FR 601, Jan. 9, 1989, as amended at 63 FR 31923, June 11, 1998]

§ 700.18   Limitations on placing rated orders.

(a) General limitations. (1) A person may not place a DO or DX rated order unless entitled to do so under this regulation.

(2) Rated orders may not be used to obtain:

(i) Delivery on a date earlier than needed;

(ii) A greater quantity of the item than needed, except to obtain a minimum procurable quantity. Separate rated orders may not be placed solely for the purpose of obtaining minimum procurable quantities on each order;

(iii) Items in advance of the receipt of a rated order, except as specifically authorized by Commerce (see §700.51(c) for information on obtaining authorization for a priority rating in advance of a rated order); or

(iv) Any of the following items unless specific priority rating authority has been obtained from a Delegate Agency or Commerce:

(A) Items for plant improvement, expansion or construction, unless they will be physically incorporated into a construction project covered by a rated order; and

(B) Production or construction equipment or items to be used for the manufacture of production equipment. [For information on requesting priority rating authority, see §700.51.]

(v) Any items related to the development of chemical or biological warfare capabilities or the production of chemical or biological weapons, unless such development or production has been authorized by the President or the Secretary of Defense.

(b) Jurisdiction limitations. (1) The priorities and allocations authority for certain items have been delegated under Executive Orders 12919 and 12742, other executive order, or Interagency Memoranda of Understanding to other agencies. Unless otherwise agreed to by the concerned agencies, the provisions of this part are not applicable to these items which include:

(i) Food resources, food resource facilities, and the domestic distribution of farm equipment and commercial fertilizer (Department of Agriculture) (The Department of Agriculture and the Department of Commerce have agreed that the Department of Defense may place rated contracts and orders for food resources in support of troops, including but not limited to, meals ready to eat (MREs), “tray-packs” (T-rations), A-rations, and B-rations);

(ii) All forms of energy, including radioisotopes, stable isotopes, source material, and special nuclear material produced in Government-owned plants or facilities operated by or for the Department of Energy (Department of Energy);

(iii) Health resources (Department of Health and Human Services);

(iv) All forms of civil transportation (Department of Transportation);

(v) Water resources (Department of Defense/U.S. Army Corps of Engineers); and

(vi) Communications services (National Communications System under Executive Order 12472 of April 3, 1984).

(2) The jurisdiction of the Department of Commerce and the Departments of Energy and Agriculture over certain specific items included in the categories listed above has been clarified by Interagency Memoranda of Understanding.

(3) The following items under the jurisdiction of Commerce are currently excluded from the rating provisions of this regulation; however, these items are subject to Commerce Directives. These excluded items are:

Copper raw materials

Crushed stone

Gravel

Sand

Scrap

Slag

Steam heat, central

Waste paper

[49 FR 30414, July 30, 1984. Redesignated at 54 FR 601, Jan. 9, 1989, as amended at 63 FR 31923, June 11, 1998; 71 FR 39528, July 13, 2006]

Browse Previous |  Browse Next























































chanrobles.com





ChanRobles Legal Resources:

ChanRobles On-Line Bar Review

ChanRobles Internet Bar Review : www.chanroblesbar.com

ChanRobles MCLE On-line

ChanRobles Lawnet Inc. - ChanRobles MCLE On-line : www.chanroblesmcleonline.com