18 C.F.R. § 12.34   Approval of independent consultant.


Title 18 - Conservation of Power and Water Resources


Title 18: Conservation of Power and Water Resources
PART 12—SAFETY OF WATER POWER PROJECTS AND PROJECT WORKS
Subpart D—Inspection by Independent Consultant

Browse Previous |  Browse Next

§ 12.34   Approval of independent consultant.

At least 60 days before the initiation of an inspection under this subpart, the licensee must submit to the Director of the Office of Energy Projects Licensing for approval, with a copy to the Regional Engineer, a detailed resume that (a) describes the experience of the independent consultant; and, (b) shows that the consultant is an independent consultant as defined in §12.31(a).

[Order 122, 46 FR 9036, Jan. 28, 1981, as amended at 49 FR 29370, July 20, 1984]

Browse Previous |  Browse Next






















chanrobles.com


ChanRobles Legal Resources:

ChanRobles On-Line Bar Review

ChanRobles Internet Bar Review : www.chanroblesbar.com

ChanRobles MCLE On-line

ChanRobles Lawnet Inc. - ChanRobles MCLE On-line : www.chanroblesmcleonline.com