18 C.F.R. § 157.38 Pre-approval procedures.
Title 18 - Conservation of Power and Water Resources
No later than 90 days prior to providing the notice of open season required by §157.34(a), a prospective applicant must file, for Commission approval, a detailed plan for conducting an open season in conformance with this subpart. The prospective applicant's plan shall include the proposed notice of open season. Upon receipt of a request for such a determination, the Secretary of the Commission shall issue a notice of the request, which will then be published in the [Order 2005–A, 70 FR 35026, June 16, 2005]
Title 18: Conservation of Power and Water Resources
PART 157—APPLICATIONS FOR CERTIFICATES OF PUBLIC CONVENIENCE AND NECESSITY AND FOR ORDERS PERMITTING AND APPROVING ABANDONMENT UNDER SECTION 7 OF THE NATURAL GAS ACT
Subpart B—Open Seasons for Alaska Natural Gas Transportation Projects
§ 157.38 Pre-approval procedures.