18 C.F.R. § 430.13   Protected area permits for new withdrawals.


Title 18 - Conservation of Power and Water Resources


Title 18: Conservation of Power and Water Resources
PART 430—GROUND WATER PROTECTION AREA: PENNSYLVANIA

Browse Previous |  Browse Next

§ 430.13   Protected area permits for new withdrawals.

Any person, firm, corporation or other entity who proposes to develop a new ground water withdrawal or expand an existing ground water withdrawal for any purpose within the Southeastern Pennsylvania Ground Water Protected Area shall be required to obtain a protected area permit under this regulation if the proposed new or increased rate of withdrawal from a well or group of wells operated as a system average more than 10,000 gallons per day over a 30-day period. Whenever the Executive Director, upon investigation or upon a reference from a state or federal agency, determines that a new or increased withdrawal from a group of wells within the protected area, whether or not such wells are operated as a system, may have a substantial effect on the water resources of the basin or is likely to have a significant adverse effect on other water uses within the protected area, the Commission may direct a notice to the owners or sponsors of such wells, and require such owners or sponsors to apply for and obtain a protected area permit under this regulation.

(a) Applications for a protected area permit shall be submitted to the Commission on forms approved by the Executive Director. Each application shall be accompanied by the following information:

(1) A map indicating the location of existing wells and perennial streams.

(2) A written report prepared by a hydrogeologist describing the expected effects of the proposed withdrawal on existing wells, flows of perennial streams and the long-term lowering of ground water levels.

(3) A log showing the nature of subsurface material encountered during the construction and installation of the exploratory or production well(s).

(4) The detailed results of extended pump tests, of not less than 48 hours duration, and records of observations during such pump tests from representative monitoring wells.

(b) Applications for a protected area permits whose daily average withdrawal during any calendar month is in excess of 10,000 gallons shall be accompanied by an application fee of $100. Government agencies shall be exempt from such application fee.

(c) If the application for a protected area permit is for a daily average withdrawal during any calendar month in excess of 100,000 gallons, it shall be accompanied by such other information or exhibits required by Article 3 of the Commission's Rules of Practice and Procedure. In such cases, only the application fee required by the Rules will be assessed.

(d) To qualify for approval of a protected area permit, the owner or sponsor of the proposed withdrawal shall demonstrate that:

(1) The proposed withdrawal is consistent with the Commission's Comprehensive Plan and the policies and purposes of these regulations.

(2) Opportunities to satisy water requirements on a timely basis from existing available supplies and facilities have been explored and found infeasible.

(3) The proposed withdrawal, in conjunction with other withdrawals in the applicable ground water basin, will not exceed withdrawal limits of a ground water basin, aquifer or aquifer system.

(4) The proposed withdrawal will not significantly impair or reduce the flow of perennial streams in the area.

(5) Existing ground and surface water withdrawals will not be adversely impacted, or will be otherwise assured of adequate supplies in accordance with the requirements of §430.19 of this part.

(6) The proposed withdrawal will not cause substantial, permanent adverse impact to the overlying environment.

(7) The owner or sponsor has adopted and will implement conservation and management programs as required by §430.15 of this part.

(e) Ground water withdrawals for space heating or cooling purposes that are less than 100,000 gallons per day shall be exempt from obtaining a protected area permit provided that the water withdrawn is returned locally, and to the same ground water basin and aquifer system from which it is withdrawn, undiminished in quantity and quality (except temperature). Ground water withdrawals for space heating or cooling that are subsequently used for commercial or industrial water supply purposes are subject to Commission withdrawal and wastewater discharge regulations. Ground water withdrawals exempted pursuant to this subsection shall be subject to the registration requirements of §430.17.

(f) All ground water withdrawal projects exempted by subsection “e” above shall be constructed in conformance with accepted industry practice and as a minimum shall comply with the following standards:

(1) All wells shall be drilled by a Pennsylvania licensed well driller and a Water Well Inventory Report shall be completed and filed with the Pennsylvania Department of Environmental Resources (PADER);

(2) No wells shall be located within a 100-year floodway;

(3) All wells shall have top of casing extended a minimum of one foot above the 100-year flood elevation;

(4) All wells shall have the casing protruding a minimum of six inches above the immediate surrounding grade;

(5) The area around all wells or well pits shall be constructed and/or graded to prevent the entrance of surface waters;

(6) All wells shall be accessible for inspection and shall have an access hole for water level measurements;

(7) In order to protect against significant leaks of refrigerant, all ground water heat pump systems shall be equipped with an automatic shutdown device that senses abnormally low or abnormally high refrigerant pressures;

(8) Any drilled well holes that are abandoned shall be sealed with a minimum of ten feet of cement grout. Additional seals may be required to separate different water-bearing zones.

(g) Protected area permits shall be approved or disapproved by the Executive Director with the concurrence of the Pennsylvania member of the Commission or his alternate.

(h) Dockets and protected area permits may be issued for a duration of up to ten years and shall specify the maximum total withdrawals that must not be exceeded during any consecutive 30-day period. Such maximum total withdrawals shall be based on demands projected to occur during the duration of the docket or protected area permit.

(i) Ground water withdrawal limits shall be defined for subbasins in accordance with the provisions of (i)(1) or (2) of this section. The limits for specific subbasins are set forth in (i)(3) of this section.

(1) Baseflow frequency analyses shall be conducted for all subbasins in the Southeastern Pennsylvania Ground Water Protected Area. The analyses shall determine the 1-year-in-25 average annual baseflow rate. The 1-year-in-25 average annual baseflow rate shall serve as the maximum withdrawal limit for net annual ground water withdrawals for subbasins. If net annual ground water withdrawals exceed 75 percent of this rate for a subbasin, such a subbasin shall be deemed “potentially stressed.” The Commission shall maintain a current list of net annual ground water withdrawals for all subbasins. “Net” annual ground water withdrawals includes total ground water withdrawals less total water returned to the ground water system of the same subbasin.

(2) Upon application by the appropriate governmental body or bodies, the withdrawal limits criteria set forth in (i)(1) of this section may be revised by the Commission to provide additional protection for any subbasin identified in (i)(3) of this section with streams or stream segments designated by the Commonwealth of Pennsylvania as either “high quality,” or “exceptional value,” or “wild,” or “scenic,” or “pastoral,” or to correspond with more stringent requirements in integrated resource plans adopted and implemented by all municipalities within a subbasin identified in (i)(3) of this section. Integrated resource plans shall be developed according to sound principles of hydrology. Such plans shall at a minimum assess water resources and existing uses of water; estimate future water demands and resource requirements; evaluate supply-side and demand-side alternatives to meet water withdrawal needs; assess options for wastewater discharge to subsurface formations and streams; consider stormwater and floodplain management; assess the capacity of the subbasin to meet present and future demands for withdrawal and nonwithdrawal uses such as instream flows; identify potential conflicts and problems; incorporate public participation; and outline plans and programs including land use ordinances to resolve conflicts and meet needs. Integrated resource plans shall be adopted and implemented by all municipalities within a subbasin and incorporated into each municipality's Comprehensive Plan.

(3)(i) The potentially stressed levels and withdrawal limits for all delineated basins and subbasins are set forth below:

 ------------------------------------------------------------------------                                            Potentially                Subbasin                  Stressed (mgy)    Withdrawal                                                \1\         Limit (mgy)------------------------------------------------------------------------                          Neshaminy Creek Basin------------------------------------------------------------------------West Branch Neshaminy Creek Basin.......            1054            1405Pine Run Basin..........................             596             795North Branch Neshaminy Creek............             853            1131Doylestown Subbasin Neshaminy Creek.....             710             946Warwick Subbasin Neshaminy Creek........             889            1185Warrington Subbasin Little Neshaminy                 505             673 Creek..................................Park Creek Basin........................             582             776Warminster Subbasin Little Neshaminy                1016            1355 Creek..................................Mill Creek Basin........................            1174            1565Northampton Subbasin Neshaminy Creek....             596             794Newtown Creek...........................             298             397Core Creek Basin........................             494             658Ironworks Creek Basin...................             326             434Schuylkill River Basin..................            3026           4034                 Lower Section Subbasin Neshaminy Creek------------------------------------------------------------------------Hay Creek...............................             974            1299Lower Reach Manatawny-Ironstone Creek...            1811            2414Pigeon Creek............................             611             815Schuylkill-Crow Creek...................            1157            1543Schuylkill-Mingo Creek..................             671             895Schuylkill-Plymouth-Mill Creeks.........            4446            5929Schuylkill-Sixpenny Creek...............            1490            1987Schuylkill-Sprogels Run.................            1091            1455Schuylkill-Stony Creek..................             687             916Schuylkill-Trout Creek..................            1082            1443Stony Creek.............................            1242            1655Valley Creek............................            1865            2486                  French and Pickering Creek Subbasins------------------------------------------------------------------------Lower Reach French Creek................             634             845Lower Reach Pickering Creek.............            1716            2288Middle Reach French Creek...............            1608            2145South Branch French Creek...............            1044            1393Upper Reach French Creek................            1295            1726Upper Reach Pickering Creek.............            1358           1811                 Perkiomen and Skippack Creek Subbasins------------------------------------------------------------------------East Branch Perkiomen-Indian Creeks.....             633             844East Branch Perkiomen-Mill Creeks.......             720             961East Branch Perkiomen-Morris Run........            1214            1619Hosensack-Indian Creeks.................            1257            1676Lower Reach Skippack Creek..............            1069            1426Perkiomen-Deep Creeks...................            1047            1396Perkiomen-Lodal Creeks..................            1200            1600Perkiomen-Macoby Creek..................            1252            1669Swamp-Middle Creeks.....................            1423            1898Swamp-Minister Creeks...................             547             730Swamp-Scioto Creeks.....................             746             994Towamencin Creek........................             466             622Unami-Licking Creeks....................             992            1322Unami-Ridge Valley Creeks...............            1068            1424Upper Reach Perkiomen Creek.............            1223            1631Upper Reach Skippack Creek..............             813            1084West Branch Perkiomen Creek.............            1566           2088                          Delaware River Basin------------------------------------------------------------------------Jericho Creek...........................             421             562Mill Creek..............................            1600            2134Paunnacussing Creek.....................             513             684Pidcock Creek...........................             563             751Upper Reach Cobbs Creek.................             871            1161Upper Reach Crum Creek..................            1290            1721Upper Reach Darby Creek.................            1625            2167Upper Reach East Branch Chester Creek...            1865            2487Upper Reach Frankford Creek.............            1414            1886Upper Reach Poquessing Creek............            1008            1344Upper Reach Ridley Creek................            1707            2275                            Tohickon Subbasin------------------------------------------------------------------------Tohickon-Beaver-Morgan Creeks...........            1156            1541Tohickon-Deep Run.......................             956            1274Tohickon-Geddes-Cabin Runs..............             602             803Tohickon-Lake Nockamixon................             556             741Tohickon-Three Mile Run.................             726            968                   Pennypack and Wissahickon Subbasins------------------------------------------------------------------------Lower Reach Wissahickon Creek...........            2750            3666Upper Reach Wissahickon Creek...........            1302            1736Middle Reach Pennypack Creek............            1295            1727Upper Reach Pennypack Creek.............            1358           1811                        Brandywine Creek Subbasin------------------------------------------------------------------------East Branch Brandywine-Taylor Run.......            1054            1405Middle Reach Brandywine Creek...........             823            1098Upper Reach Brandywine Creek............            1614            2153West Branch Brandywine-Beaver Run.......            2110            2813West Branch Brandywine-Broad Run........            2380            3173West Valley Creek.......................            1673           2231                             Lehigh Subbasin------------------------------------------------------------------------Upper Reach Saucon Creek................             946            1262------------------------------------------------------------------------\1\ mgy means million gallons per year.

(ii) Subject to public notice and hearing, this section may be updated or revised based upon new and evolving information on hydrology and streamflow and ground water monitoring or in accordance with paragraph (i)(2) of this section.

(j) Upon its determination that a subbasin is potentially stressed, the Commission shall notify all ground water users in the subbasin withdrawing 10,000 gallons per day or more during any 30-day period of its determination. If any such users have not obtained a docket or protected area permit from the Commission, they shall be required to apply to the Commission within 60 days of notification.

(k) In potentially stressed subbasins, dockets and protected area permit applications for new or expanded ground water withdrawals must include one or more programs to mitigate the adverse impacts of the new or expanded ground water withdrawal. The eligible programs are noted below. If the remainder of the application and the program(s) submitted are acceptable, the withdrawal may be approved by the Commission for an initial three-year period. The applicant shall implement the program(s) immediately upon Commission approval. If after the three-year period the program(s) is deemed successful by the Commission, the docket or permit duration may be extended for up to 10 years. The project sponsor shall be required to continue the program(s) for the duration of the docket or permit.

(1) A conjunctive use program that demonstrates the applicant's capability to obtain at least 15 percent of its average annual system usage from a reliable surface water supply. An acceptable program shall include either reservoir storage or an interconnection with a surface water supplier and an agreement or contract to purchase water from the supplier for the duration of the docket or permit.

(2) A water conservation program that exceeds the requirements of §430.15. For existing water utilities, the program shall reduce average annual per capita water usage by at least five percent. All conservation programs shall include water conservation pricing, either inclining block rates, seasonal rates, or excess-use surcharges, and plumbing fixture rebate or retrofit components. For self-supplied users, the program shall include water efficient technologies such as recycling, reuse, xeriscaping, drip or micro irrigation, or other innovative technology approved by the Commission.

(3) A program to monitor and control ground water infiltration to the receiving sewer system. The program must quantify ground water infiltration to the system and document reductions in infiltration. The program should include such measures as leakage surveys of sewer mains, metering of sewer flows in mains and interceptors, analysis of sewer system flows to quantify infiltration, and remedial measures such as repair of leaks and joints, main lining, and main replacement.

(4) An artificial recharge or spray irrigation program that demonstrates a return of at least 60 percent of the total new or expanded annual withdrawal to the same ground water basin and aquifer system from which it is withdrawn. The program shall not impair ground water quality.

(5) An alternative program approved by the Commission to mitigate the adverse impacts of the new or expanded ground water withdrawal.

(l) The durations of all existing dockets and protected area permits may be extended by the Commission for an additional five years if the docket or permit holder successfully implements in either (k)(1) or (k)(2) of this section. If the docket or permit holder successfully implements both options, the docket or permit may be extended for an additional ten years. The Executive Director shall notify all docket and permit holders potentially affected by this resolution of their right to file an application to determine their eligibility for extension.

(m) It is the policy of the Commission to prevent, to the extent reasonably possible, net annual ground water withdrawals from exceeding the maximum withdrawal limit. An application for a proposed new or expanded ground water withdrawal that would result in net annual ground water withdrawals exceeding the maximum withdrawal limit established in paragraph (i)(3) of this section shall set forth the applicant's proposal for complying with the Commission's policy, with such supporting documentation as may be required by the Executive Director. Notification of the application shall be given to all affected existing water users who may also submit comments or recommendations for consideration by the Commission on the pending application. In taking action upon the application, the Commission shall give consideration to the submissions from the applicant and affected water users. If the Commission determines that it is in the public interest to do so, it may reduce the total of proposed and existing ground water withdrawals within a subbasin to a level at or below the withdrawal limit. Unless otherwise determined by the Commission, docket and permit holders shall share equitably in such reductions.

[46 FR 24, Jan. 2, 1981, as amended at 50 FR 5973, Feb. 13, 1985; 63 FR 6477, Feb. 9, 1998; 64 FR 35566, July 1, 1999]