18 C.F.R. § 1308.24 Undue delay in Contracting Officer's decision.
Title 18 - Conservation of Power and Water Resources
(a) If there is an undue delay by a Contracting Officer in issuing a decision on a claim, the Contractor may request the Chairman to direct the Contracting Officer to issue a decision within a specified period of time. (b) A request under this section shall: (1) Be in writing; (2) State the date on which the claim was submitted to the Contracting Officer. (3) State the date suggested for issuance of a decision by the Contracting Officer. (c) TVA may reply to a motion under this section within 5 days after its receipt. (d) The Chairman shall issue a written decision on the request. If granted, the decision shall specify the date by which the Contracting Officer's decision is to be rendered, and a copy shall be served on the Contracting Officer.
Title 18: Conservation of Power and Water Resources
PART 1308—CONTRACT DISPUTES
Subpart C—Board of Contract Appeals
§ 1308.24 Undue delay in Contracting Officer's decision.