§ 450.216   Statewide transportation improvement program (STIP).

(a) Each State shall develop a statewide transportation improvement program for all areas of the State. In case of difficulties in developing the STIP portion for a particular area, e.g., metropolitan area, Indian tribal lands, etc., a partial STIP covering the rest of the State may be developed. The portion of the STIP in a metropolitan planning area (the metropolitan TIP developed pursuant to subpart C of this part) shall be developed in cooperation with the MPO. To assist this process, the State will need to provide MPOs with estimates of available Federal and State funds which the MPO can utilize in developing the metropolitan TIP. Metropolitan planning area TIPs shall be included without modification in the STIP, directly or by reference, once approved by the MPO and the Governor and after needed conformity findings are made. Metropolitan TIPs in nonattainment and maintenance areas are subject to the FHWA and the FTA conformity findings before their inclusion in the STIP. In nonattainment and maintenance areas outside metropolitan planning areas, Federal findings of conformity must be made prior to placing projects in the STIP. The State shall notify the appropriate MPO, local jurisdictions, Federal land agency, Indian tribal government, etc. when a TIP including projects under the jurisdiction of the agency has been included in the STIP. All title 23 and Federal Transit Act fund recipients will share information as projects in the STIP are implemented. The Governor shall provide for public involvement in development of the STIP as required by §450.212. In addition, the STIP shall:

(1) Include a list of priority transportation projects proposed to be carried out in the first 3 years of the STIP. Since each TIP is approved by the Governor, the TIP priorities will dictate STIP priorities for each individual metropolitan area. As a minimum, the lists shall group the projects that are to be undertaken in each of the years, e.g., year 1, year 2, year 3;

(2) Cover a period of not less than 3 years, but may at State discretion cover a longer period. If the STIP covers more than 3 years, the projects in the additional years will be considered by the FHWA and the FTA only as informational;

(3) Contain only projects consistent with the statewide plan developed under §450.214;

(4) In nonattainment and maintenance areas, contain only transportation projects found to conform, or from programs that conform, to the requirements contained in 40 CFR part 51;

(5) Be financially constrained by year and include sufficient financial information to demonstrate which projects are to be implemented using current revenues and which projects are to be implemented using proposed revenue sources while the system as a whole is being adequately operated and maintained. In nonattainment and maintenance areas, projects included in the first two years of the current STIP/TIP shall be limited to those for which funds are available or committed. In the case of proposed funding sources, strategies for ensuring their availability shall be identified;

(6) Contain all capital and non-capital transportation projects (including transportation enhancements, Federal lands highways projects, trails projects, pedestrian walkways, and bicycle transportation facilities), or identified phases of transportation projects, proposed for funding under the Federal Transit Act (49 U.S.C. app. 1602, 1607a, 1612 and 1614) and/or title 23, U.S.C. excluding:

(i) Safety projects funded under section 402 of the Surface Transportation Assistance Act of 1982, as amended (49 U.S.C. app. 2302);

(ii) IVHS planning grants funded under section 6055(b) of the Intermodal Surface Transportation Efficiency Act of 1991 (Pub. L. 102–240, 105 Stat. 1914);

(iii) Transit planning grants funded under section 8 or 26 of the Federal Transit Act (49 U.S.C. app. 1607 and 1622);

(iv) Metropolitan planning projects funded under 23 U.S.C. 104(f);

(v) State planning and research projects funded under 23 U.S.C. 307(c)(1) (except those funded with NHS, STP and minimum allocation (MA) funds that the State and MPO for a metropolitan area agree should be in the TIP and consequently must be in the STIP); and

(vi) Emergency relief projects (except those involving substantial functional, locational or capacity changes);

(7) Contain all regionally significant transportation projects requiring an action by the FHWA or the FTA whether or not the projects are to be funded with title 23, U.S.C. or Federal Transit Act funds, e.g., addition of an interchange to the Interstate System with State, local and/or private funds, demonstration projects not funded under title 23, U.S.C., or the Federal Transit Act. (The STIP should, for information purposes, include all regionally significant transportation projects proposed to be funded with Federal funds other than those administered by the FHWA or the FTA. It should also include, for information purposes, if appropriate and cited in any TIPs, all regionally significant projects, to be funded with non-Federal funds);

(8) Include for each project the following:

(i) Sufficient descriptive material (i.e., type of work, termini, length, etc.) to identify the project or phase;

(ii) Estimated total cost;

(iii) The amount of Federal funds proposed to be obligated during each program year;

(iv) For the first year, the proposed category of Federal funds and source(s) of non-Federal funds;

(v) For the second and third years, the likely category or possible categories of Federal funds and sources of non-Federal funds;

(vi) Identification of the agencies responsible for carrying out the project; and

(9) For non-metropolitan areas, include in the first year only those projects which have been selected in accordance with the project selection requirements in §450.222(c).

(b) Projects that are not considered to be of appropriate scale for individual identification in a given program year may be grouped by function, work type, and/or geographic area using the applicable classifications under 23 CFR 771.117 (c) and (d) and/or 40 CFR part 51.

(c) Projects in any of the first three years of the STIP may be moved to any other of the first three years of the STIP subject to the project selection requirements of §450.222.

(d) The STIP may be amended at any time under procedures agreed to by the cooperating parties consistent with the procedures established in this section (for STIP development), in §450.212 (for public involvement) and in §450.220 (for the FHWA and the FTA approval).

(e) In developing the statewide transportation improvement program, affected local officials with responsibility for transportation shall be involved on a consultation basis for the portions of the program in non-metropolitan areas of the State.

[58 FR 58064, Oct. 28, 1993, as amended at 68 FR 3181, Jan. 23, 2003]

Browse Previous |  Browse Next






















chanrobles.com


ChanRobles Legal Resources:

ChanRobles On-Line Bar Review

ChanRobles Internet Bar Review : www.chanroblesbar.com

ChanRobles MCLE On-line

ChanRobles Lawnet Inc. - ChanRobles MCLE On-line : www.chanroblesmcleonline.com