23 C.F.R. § 771.113   Timing of Administration activities.


Title 23 - Highways


Title 23: Highways
PART 771—ENVIRONMENTAL IMPACT AND RELATED PROCEDURES

Browse Previous |  Browse Next

§ 771.113   Timing of Administration activities.

(a) The Administration in cooperation with the applicant will perform the work necessary to complete a FONSI or an EIS and comply with other related environmental laws and regulations to the maximum extent possible during the NEPA process. This work includes environmental studies, related engineering studies, agency coordination and public involvement. However, final design activities, property acquisition (with the exception of hardship and protective buying, as defined in §771.117(d)), purchase of construction materials or rolling stock, or project construction shall not proceed until the following have been completed:

(1)(i) The action has been classified as a categorical exclusion (CE), or

(ii) A FONSI has been approved, or

(iii) A final EIS has been approved and available for the prescribed period of time and a record of decision has been signed;

(2) For actions proposed for FHWA funding, the FHWA Division Administrator has received and accepted the certifications and any required public hearing transcripts required by 23 U.S.C. 128;

(3) For activities proposed for FHWA funding, the programming requirements of 23 CFR part 450, subpart B, and 23 CFR part 630, subpart A, have been met.

(b) For FHWA, the completion of the requirements set forth in paragraphs (a)(1) and (2) of this section is considered acceptance of the general project location and concepts described in the environmental document unless otherwise specified by the approving official. However, such approval does not commit the Administration to approve any future grant request to fund the preferred alternative.

(c) Letters of Intent issued under the authority of 49 U.S.C. 5309(g) are used by FTA to indicate an intention to obligate future funds for multi-year capital transit projects. Letters of Intent will not be issued by FTA until the NEPA process is completed.

[52 FR 32660, Aug. 28, 1987; 53 FR 11066, Apr. 5, 1988, as amended at 70 FR 24469, May 9, 2005]

Browse Previous |  Browse Next






















chanrobles.com


ChanRobles Legal Resources:

ChanRobles On-Line Bar Review

ChanRobles Internet Bar Review : www.chanroblesbar.com

ChanRobles MCLE On-line

ChanRobles Lawnet Inc. - ChanRobles MCLE On-line : www.chanroblesmcleonline.com