24 C.F.R. § 511.75   Disbursement of rental rehabilitation grant amounts: Cash and Management Information System.


Title 24 - Housing and Urban Development


Title 24: Housing and Urban Development
PART 511—RENTAL REHABILITATON GRANT PROGRAM
Subpart H—Grant Administration

Browse Previous |  Browse Next

§ 511.75   Disbursement of rental rehabilitation grant amounts: Cash and Management Information System.

(a) General. Rental Rehabilitation grants are managed through HUD's C/MI System for the Rental Rehabilitation Program. The C/MI System is a computerized system which manages program funds, disburses grant amounts, and collects and reports data on properties and tenants assisted under the Program.

(b) Project set-up. (1) After the grantee executes the Grant Agreement, complies with the requirements under part 58 of this title for release of funds, and submits the appropriate security documents, the grantee may identify (set-up) specific local projects in the C/MI System. State recipients are also granted access to the C/MI System for projects upon designation by the State and submission of the appropriate security documents. Within 12 calendar days of project set-up, grantees and State recipients are required to submit a Pre-Rehabilitation Report to HUD for each project set-up in the C/MI System. Until an acceptable Pre-Rehabilitation Report is received and entered in the C/MI System, grant amounts for the project are not considered “committed,” as defined in §511.2, and, therefore, are subject to deobligation to the extent authorized by 24 CFR 511.33(c).

(2) Beginning in Fiscal Year 1991, if Pre-Rehabilitation Reports are not received within 20 days of the project set-up call, the project will be cancelled automatically by the C/MI System. In addition, projects which have been committed in the C/MI System for 6 months without an initial disbursement of funds will be automatically cancelled by the C/MI System.

(c) Disbursement of rental rehabilitation grant amounts. After an acceptable Pre-Rehabilitation Report is entered into the C/MI System, obligated grant amounts may be drawn down for the project by the grantee or State recipient by electronic funds transfer to the designated depository institution of the grantee or State recipient within 48 to 72 hours of the disbursement request. Grant amounts for eligible administrative costs may be similarly drawn down by grantees by electronic funds transfer to their designated depository institutions, but State recipients are not permitted to draw down State grant amounts for administrative expenses. Any drawdown is conditioned upon the submission of satisfactory information by the grantee or State recipient about the project or the administrative expenses and compliance with other procedures specified by HUD in HUD's forms and issuances concerning the Rental Rehabilitation Program Cash and Management Information System. Copies of these forms and issuances may be obtained from HUD Field Offices. Drawdowns shall be requested by the grantee or State recipient as closely as possible to the time they are needed by a grantee or State recipient and the owner to pay eligible project costs or by a grantee to pay eligible administrative costs. Drawdowns for project costs shall be requested only for work or services that have been satisfactorily performed, or materials that are acceptable. After receipt in the grantee or State recipient's depository account, grant amounts for project costs shall immediately be disbursed by the grantee or State recipient and the owner in payment for eligible project costs and shall not be disbursed at any time, relative to a project's matching funds, in any greater proportion than the proportion of rental rehabilitation grant amounts to matching funds for the project.

(d) Payment vouchers. As post-documentation of each drawdown, a grantee or State recipient must submit to HUD a payment voucher, for each drawdown made by HUD, in the form required for the C/MI System. If the drawdown was for eligible project costs and the payment voucher is not received within ten calendar days of the drawdown, the grantee or State recipient will be suspended from setting up new projects until the required payment voucher is received by HUD. If the drawdown was for administrative costs and the payment voucher is not received within ten calendar days of the drawdown, the grantee will not be allowed to make another drawdown for administrative costs until the payment voucher is received.

(e) Submission of project completion reports. After the final draw for a project, a Project Completion Report must be submitted to HUD within 90 days of the drawdown request. However, for projects rehabilitated pursuant to §511.11(c)(2) (publicly owned project at the time of commitment), the Project Completion Report must be submitted within 90 days of the final draw, but not later than 2 years and 90 days after the date of commitment. If a satisfactory Project Completion Report is not submitted by the due date, HUD will suspend further project set-ups for the grantee or State recipient. Project set-ups will remain suspended until a satisfactory Project Completion Report is received and entered into the C/MI System.

(Approved by the Office of Management and Budget under control number 2506–0080)

Browse Previous |  Browse Next






















chanrobles.com


ChanRobles Legal Resources:

ChanRobles On-Line Bar Review

ChanRobles Internet Bar Review : www.chanroblesbar.com

ChanRobles MCLE On-line

ChanRobles Lawnet Inc. - ChanRobles MCLE On-line : www.chanroblesmcleonline.com