§ 203.65   How long will MMS take to evaluate my application?

(a) We will determine within 20 working days if your application for royalty relief is complete. If your application is incomplete, we will explain in writing what it needs. If you withdraw a complete application, you may reapply.

(b) We will evaluate your first application on a field within 180 days, evaluate your first application on a development project or an expansion project within 150 days and evaluate a redetermination under §203.75 within 120 days after we determine that it is complete.

(c) We may ask to extend the review period for your application under the conditions in the following table.

 ------------------------------------------------------------------------                If_                              Then we may_------------------------------------------------------------------------We need more records to audit sunk   Ask to extend the 120-day or 180- costs.                               day evaluation period. The                                      extension we request will equal                                      the number of days between when                                      you receive our request for                                      records and the day we receive the                                      records.We cannot evaluate your application  Add another 30 days. We may add for a valid reason, such as          more than 30 days, but only if you missing vital information or         agree. inconsistent or inconclusive supporting data.We need more data, explanations, or  Ask to extend the 120-day or 180- revision.                            day evaluation period. The                                      extension we request will equal                                      the number of days between when                                      you receive our request and the                                      day we receive the information.------------------------------------------------------------------------

(d) We may change your assumptions under §203.62 if our technical evaluation reveals others that are more appropriate. We may consult with you before a final decision and will explain any changes.

(e) We will notify all designated lease operators within a field when royalty relief is granted.

[63 FR 2618, Jan. 16, 1998, as amended at 67 FR 1875, Jan. 15, 2002]