§ 148.276   When must the application be approved or denied?

(a) In 33 U.S.C. 1504, the Deepwater Port Act provides strict timelines for action on a license application, which if closely observed can lead to action in just under 1 year. The Coast Guard can recommend that MARAD suspend the process if an applicant fails to provide timely information or requests additional time to comply with a request.

(b) The Coast Guard must conduct public hearings in each adjacent Coastal State within 240 days of publication of the notice of receipt of a deepwater port application.

(c) An application must be approved or denied within 90 days after the close of the public hearing period specified in paragraph (b) of this section.

Browse Next


chanrobles.com


ChanRobles Legal Resources:

ChanRobles On-Line Bar Review

ChanRobles Internet Bar Review : www.chanroblesbar.com

ChanRobles MCLE On-line

ChanRobles Lawnet Inc. - ChanRobles MCLE On-line : www.chanroblesmcleonline.com