33 C.F.R. § 263.18 Program completion-time objectives.
Title 33 - Navigation and Navigable Waters
To provide a Program responsive to local needs, the following target (maximum) completion time objectives are established and should be used to the extent feasible, in scheduling work and programming funds. Shortening of these objectives is encouraged for specific studies and projects when appropriate. However, high standards of planning, design and construction are not to be sacrificed. Attainment of completion-time objectives through intensive management is to be a major concern for those elements and individuals given Program management responsibilities in §263.16 of this regulation.
Title 33: Navigation and Navigable Waters
PART 263—CONTINUING AUTHORITIES PROGRAMS
Subpart A—General
§ 263.18 Program completion-time objectives.
Program Authorities, Completion Times in Months------------------------------------------------------------------------ 205, 107, Emergency 103, and 208 and 14 14 and 3 111 \1\------------------------------------------------------------------------(a) Completion of recon and 2 1 2 submission of funding request or negative report to OCE.............(b) Completion of feasibility study 16 9 (\2\ ) by reporting officer and preparation of DPR.................(c) Review of DPR or recon report by 2 1 .5 division engineer, (including provisions of § 263.15(f))....(d) Review of DPR or recon report by 2 1 .5 OCE................................(e) Completion of project 18 12 3 construction (including plans and specifications), after project approval........................... -----------------------------------(f) Total completion-time objective. 40 24 6------------------------------------------------------------------------\1\ The decision to utilize a recon report or DPR for recommending a project under sec. 14 authority is delegated to the division engineer (§ 263.17(b)(3)).\2\ Not applicable.
Browse Previous |
Browse Next