43 C.F.R. § 11.91   How does the authorized official seek recovery of the assessed damages from the potentially responsible party?


Title 43 - Public Lands: Interior


Title 43: Public Lands: Interior
PART 11—NATURAL RESOURCE DAMAGE ASSESSMENTS
Subpart F—Post-Assessment Phase

Browse Previous |  Browse Next

§ 11.91   How does the authorized official seek recovery of the assessed damages from the potentially responsible party?

(a) At the conclusion of the assessment, the authorized official must present to the potentially responsible party a demand in writing for the damages determined in accordance with this part and the reasonable cost of the assessment. [See §11.92(b) to determine how the authorized official must adjust damages if he or she plans to place recovered funds in a non-interest-bearing account.] The authorized official must deliver the demand in a manner that establishes the date of receipt. The demand shall adequately identify the Federal or State agency or Indian tribe asserting the claim, the general location and description of the injured resource, the type of discharge or release determined to have resulted in the injuries, and the damages sought from that party.

(b) Report of assessment. The demand letter shall include the Report of Assessment as an attachment.

(c) Rebuttable presumption. When performed by a Federal or State official in accordance with this part, the natural resource damage assessment and the resulting Damage Determination supported by a complete administrative record of the assessment including the Report of Assessment as described in §11.90 of this part shall have the force and effect of a rebuttable presumption on behalf of any Federal or State claimant in any judicial or adjudicatory administrative proceeding under CERCLA, or section 311 of the CWA.

(d) Potentially responsible party response. The authorized official should allow at least 60 days from receipt of the demand by the potentially responsible party, with reasonable extensions granted as appropriate, for the potentially responsible party to acknowledge and respond to the demand, prior to filing suit. In cases governed by section 113(g) of CERCLA, the authorized official may include a notice of intent to file suit and must allow at least 60 days from receipt of the demand by the potentially responsible party, with reasonable extensions granted as appropriate, for the potentially responsible party to acknowledge and respond to the demand, prior to filing suit.

(e) Statute of limitations. For the purposes of section 113(g) of CERCLA, the date on which regulations are promulgated under section 301(c) of CERCLA is the date on which the later of the revisions to the type A rule and the type B rule, pursuant to State of Colorado v. United States Department of the Interior, 880 F.2d 481 (D.C. Cir. 1989), and State of Ohio v. United States Department of the Interior, 880 F.2d 432 (D.C. Cir. 1989), is published as a final rule in the Federal Register.

[53 FR 5176, Feb. 22, 1988, as amended at 59 FR 14287, Mar. 25, 1994; 61 FR 20612, May 7, 1996]

Browse Previous |  Browse Next

chanrobles.com


ChanRobles Legal Resources:

ChanRobles On-Line Bar Review

ChanRobles Internet Bar Review : www.chanroblesbar.com

ChanRobles MCLE On-line

ChanRobles Lawnet Inc. - ChanRobles MCLE On-line : www.chanroblesmcleonline.com