43 C.F.R. § 2804.26 Under what circumstances may BLM deny my application?
Title 43 - Public Lands: Interior
(a) BLM may deny your application if: (1) The proposed use is inconsistent with the purpose for which BLM manages the public lands described in your application; (2) The proposed use would not be in the public interest; (3) You are not qualified to hold a grant; (4) Issuing the grant would be inconsistent with the Act, other laws, or these or other regulations; (5) You do not have or cannot demonstrate the technical or financial capability to construct the project or operate facilities within the right-of-way; or (6) You do not adequately comply with a deficiency notice (see §2804.25(b) of this subpart) or with any BLM requests for additional information needed to process the application. (b) If BLM denies your application, you may appeal this decision under §2801.10 of this part.
Title 43: Public Lands: Interior
PART 2800—RIGHTS-OF-WAY UNDER THE FEDERAL LAND POLICY MANAGEMENT ACT
Subpart 2804—Applying for FLPMA Grants
§ 2804.26 Under what circumstances may BLM deny my application?