43 C.F.R. § 2885.14 What happens if I need a right-of-way wider than 50 feet plus the ground occupied by the pipeline and related facilities?
Title 43 - Public Lands: Interior
(a) You may apply to BLM at any time for a right-of-way wider than 50 feet plus the ground occupied by the pipeline and related facilities. In your application you must show that the wider right-of-way is necessary to: (1) Properly operate and maintain the pipeline after you have constructed it; (2) Protect the environment; or (3) Provide for public safety. (b) BLM will notify you in writing of its finding(s) and its decision on your application for a wider right-of-way. If the decision is adverse to you, you may appeal it under §2881.10 of this part.
Title 43: Public Lands: Interior
PART 2880—RIGHTS-OF-WAY UNDER THE MINERAL LEASING ACT
Subpart 2885—Terms and Conditions of MLA Grants and TUPs
§ 2885.14 What happens if I need a right-of-way wider than 50 feet plus the ground occupied by the pipeline and related facilities?