43 C.F.R. § 3137.91 When will BLM allow a well previously determined to be a non-unit well to be used in establishing or modifying a PA?
Title 43 - Public Lands: Interior
If you, as the unit operator, complete sufficient work so that a well BLM previously determined to be a non-unit well now meets the productivity criteria, you must demonstrate this to BLM within 60 calendar days after you determine that the well meets the productivity criteria. You must then modify an existing participating area or establish a new participating area (see §3137.84 of this subpart).
Title 43: Public Lands: Interior
PART 3130—OIL AND GAS LEASING: NATIONAL PETROLEUM RESERVE, ALASKA
Subpart 3137—Unitization Agreements—National Petroleum Reserve-Alaska
Participating Areas
§ 3137.91 When will BLM allow a well previously determined to be a non-unit well to be used in establishing or modifying a PA?