43 C.F.R. § 3272.10   What must I give BLM in my utilization plan?


Title 43 - Public Lands: Interior


Title 43: Public Lands: Interior
PART 3200—GEOTHERMAL RESOURCE LEASING
Subpart 3272—What is in a Utilization Plan and Facility Construction Permit?

Browse Next

§ 3272.10   What must I give BLM in my utilization plan?

Describe the proposed facilities as set out in 43 CFR 3272.11, and the anticipated environmental impacts and how you propose to mitigate those impacts, as set out at 3272.12.