43 C.F.R. § 3273.10 When do I need a site license for a utilization facility?
Title 43 - Public Lands: Interior
You must obtain a site license approved by BLM unless your facility will be located on lands leased described under 43 CFR 3273.11. Do not start building or testing your utilization facility on lands leased by BLM for geothermal resources until we have approved both your facility construction permit (See 3272.14) and your site license. The facility operator must apply for the license.