44 C.F.R. Subpart G—Public Assistance Project Administration


Title 44 - Emergency Management and Assistance


Title 44: Emergency Management and Assistance
PART 206—FEDERAL DISASTER ASSISTANCE FOR DISASTERS DECLARED ON OR AFTER NOVEMBER 23, 1988

Browse Previous |  Browse Next

Subpart G—Public Assistance Project Administration

Source:  55 FR 2304, Jan. 23, 1990, unless otherwise noted.

§ 206.200   General.

(a) Purpose. This subpart establishes procedures for the administration of Public Assistance grants approved under the provisions of the Stafford Act.

(b) What policies apply to FEMA public assistance grants? (1) The Stafford Act requires that we deliver eligible assistance as quickly and efficiently as possible consistent with Federal laws and regulations. We expect the Grantee and the subgrantee to adhere to Stafford Act requirements and to these regulations when administering our public assistance grants.

(2) The regulations entitled “Uniform Requirements for Grants and Cooperative Agreements to State and Local Governments,” published at 44 CFR part 13, place requirements on the State in its role as Grantee and gives the Grantee discretion to administer federal programs under their own procedures. We expect the Grantee to:

(i) Inform subgrantees about the status of their applications, including notifications of our approvals of Project Worksheets and our estimates of when we will make payments;

(ii) Pay the full amounts due to subgrantees as soon as practicable after we approve payment, including the State contribution required in the FEMA-State Agreement; and

(iii) Pay the State contribution consistent with State laws.

[55 FR 2304, Jan. 23, 1990, as amended at 63 FR 64425, Nov. 20, 1998; 64 FR 55160, Oct. 12, 1999]

§ 206.201   Definitions used in this subpart.

(a) Applicant means a State agency, local government, or eligible private nonprofit organization, as identified in Subpart H of this regulation, submitting an application to the Grantee for assistance under the State's grant.

(b) Emergency work means that work which must be done immediately to save lives and to protect improved property and public health and safety, or to avert or lessen the threat of a major disaster.

(c) Facility means any publicly or privately owned building, works, system, or equipment, built or manufactured, or an improved and maintained natural feature. Land used for agricultural purposes is not a facility.

(d) Grant means an award of financial assistance. The grant award shall be based on the total eligible Federal share of all approved projects.

(e) Grantee means the government to which a grant is awarded which is accountable for the use of the funds provided. The grantee is the entire legal entity even if only a particular component of the entity is designated in the grant award document. For purposes of this regulation, except as noted in §206.202, the State is the grantee.

(f) Hazard mitigation means any cost effective measure which will reduce the potential for damage to a facility from a disaster event.

(g) Permanent work means that restorative work that must be performed through repairs or replacement, to restore an eligible facility on the basis of its predisaster design and current applicable standards.

(h) Predisaster design means the size or capacity of a facility as originally designed and constructed or subsequently modified by changes or additions to the original design. It does not mean the capacity at which the facility was being used at the time the major disaster occurred if different from the most recent designed capacity.

(i) A project is a logical grouping of work required as a result of the declared major disaster or emergency. The scope of work and cost estimate for a project are documented on a Project Worksheet (FEMA Form 90–91).

(1) We must approve a scope of eligible work and an itemized cost estimate before funding a project.

(2) A project may include eligible work at several sites.

(j) Project approval means the process in which the Regional Director, or designee, reviews and signs an approval of work and costs on a Project Worksheet or on a batch of Project Worksheets. Such approval is also an obligation of funds to the Grantee.

(k) Subgrant means an award of financial assistance under a grant by a grantee to an eligible subgrantee.

(l) Subgrantee means the government or other legal entity to which a subgrant is awarded and which is accountable to the grantee for the use of the funds provided.

[55 FR 2304, Jan. 23, 1990, as amended at 63 FR 64425, Nov. 20, 1998; 64 FR 55160, Oct. 12, 1999]

§ 206.202   Application procedures.

(a) General. This section describes the policies and procedures that we use to process public assistance grants to States. Under this section the State is the Grantee. As Grantee you are responsible for processing subgrants to applicants under 44 CFR parts 13, 14, and 206, and your own policies and procedures.

(b) Grantee. You are the grant administrator for all funds provided under the Public Assistance grant program. Your responsibilities under this section include:

(1) Providing technical advice and assistance to eligible subgrantees;

(2) Providing State support for project identification activities to include small and large project formulation and the validation of small projects;

(3) Ensuring that all potential applicants are aware of available public assistance; and

(4) Submitting documents necessary for the award of grants.

(c) Request for Public Assistance (Request). The Grantee must send a completed Request (FEMA Form 90–49) to the Regional Director for each applicant who requests public assistance. You must send Requests to the Regional Director within 30 days after designation of the area where the damage occurred.

(d) Project Worksheets. (1) An applicant's authorized local representative is responsible for representing the applicant and for ensuring that the applicant has identified all eligible work and submitted all costs for disaster-related damages for funding.

(i) We or the applicant, assisted by the State as appropriate, will prepare a Project Worksheet (FEMA Form 90–91) for each project. The Project Worksheet must identify the eligible scope of work and must include a quantitative estimate for the eligible work.

(ii) The applicant will have 60 days following its first substantive meeting with us to identify and to report damage to us.

(2) When the estimated cost of work on a project is less than $1,000, that work is not eligible and we will not approve a Project Worksheet for the project. Periodically we will review this minimum approval amount for a Project Worksheet and, if needed, will adjust the amount by regulation.

(e) Grant approval. (1) Before we obligate any funds to the State, the Grantee must complete and send to the Regional Director a Standard Form (SF) 424, Application for Federal Assistance, and a SF 424D, Assurances for Construction Programs. After we receive the SF 424 and SF 424D, the Regional Director will obligate funds to the Grantee based on the approved Project Worksheets. The Grantee will then approve subgrants based on the Project Worksheets approved for each applicant.

(2) When the applicant submits the Project Worksheets, we will have 45 days to obligate Federal funds. If we have a delay beyond 45 days we will explain the delay to the Grantee.

(f) Exceptions. The following are exceptions to the procedures and time limitations outlined in paragraphs (c), (d), and (e) of this section.

(1) Grant applications. An Indian tribe or authorized tribal organization may submit a SF 424 directly to the RD when the Act authorizes assistance and a State is legally unable to assume the responsibilities that these regulations prescribe.

(2) Time limitations. The RD may extend the time limitations shown in paragraphs (c) and (d) of this section when the Grantees justifies and makes a request in writing. The justification must be based on extenuating circustances beyond the grantee's or subgrantee's control.

[64 FR 55160, Oct. 12, 1999]

§ 206.203   Federal grant assistance.

(a) General. This section describes the types and extent of Federal funding available under State disaster assistance grants, as well as limitations and special procedures applicable to each.

(b) Cost sharing. All projects approved under State disaster assistance grants will be subject to the cost sharing provisions established in the FEMA-State Agreement and the Stafford Act.

(c) Project funding—(1) Large projects. When the approved estimate of eligible costs for an individual project is $35,000 or greater, Federal funding shall equal the Federal share of the actual eligible costs documented by a grantee. Such $35,000 amount shall be adjusted annually to reflect changes in the Consumer Price Index for All Urban Consumers published by the Department of Labor.

(2) Small projects. When the approved estimate of costs for an individual project is less than $35,000, Federal funding shall equal the Federal share of the approved estimate of eligible costs. Such $35,000 amount shall be adjusted annually as indicated in paragraph (c)(1) of this section.

(d) Funding options—(1) Improved projects. If a subgrantee desires to make improvements, but still restore the predisaster function of a damaged facility, the Grantee's approval must be obtained. Federal funding for such improved projects shall be limited to the Federal share of the approved estimate of eligible costs.

(2) Alternate projects. In any case where a subgrantee determines that the public welfare would not be best served by restoring a damaged public facility or the function of that facility, the Grantee may request that the RD approve an alternate project.

(i) The alternate project option may be taken only on permanent restorative work.

(ii) Federal funding for such alternate projects will be 75 percent of the Federal share of the approved Federal estimate of eligible costs.

(iii) If soil instability at the alternate project site makes the repair, restoration or replacement of a State or local government-owned or -controlled facility infeasible, the Federal funding for such an alternate project will be 90 percent of the Federal share of the approved Federal estimate of eligible costs.

(iv) Funds contributed for alternate projects may be used to repair or expand other selected public facilities, to construct new facilities, or to fund hazard mitigation measures. These funds may not be used to pay the nonFederal share of any project, nor for any operating expense.

(v) Prior to the start of construction of any alternate project the Grantee shall submit for approval by the RD the following: a description of the proposed alternate project(s); a schedule of work; and the projected cost of the project(s). The Grantee shall also provide the necessary assurances to document compliance with special requirements, including, but not limited to floodplain management, environmental assessment, hazard mitigation, protection of wetlands, and insurance.

[55 FR 2304, Jan. 23, 1990, as amended at 66 FR 22444, May 4, 2001]

§ 206.204   Project performance.

(a) General. This section describes the policies and procedures applicable during the performance of eligible work.

(b) Advances of funds. Advances of funds will be made in accordance with 44 CFR 13.21, Payment.

(c) Time limitations for completion of work—(1) Deadlines. The project completion deadlines shown below are set from the date that a major disaster or emergency is declared and apply to all projects approved under State disaster assistance grants.

                          Completion Deadlines------------------------------------------------------------------------                         Type of work                            Months------------------------------------------------------------------------Debris clearance..............................................         6Emergency work................................................         6Permanent work................................................        18------------------------------------------------------------------------

(2) Exceptions. (i) The Grantee may impose lesser deadlines for the completion of work under paragraph (c)(1) of this section if considered appropriate.

(ii) Based on extenuating circumstances or unusual project requirements beyond the control of the subgrantee, the Grantee may extend the deadlines under paragraph (c)(1) of this section for an additional 6 months for debris clearance and emergency work and an additional 30 months, on a project by project basis for permanent work.

(d) Requests for time extensions. Requests for time extensions beyond the Grantee's authority shall be submitted by the Grantee to the RD and shall include the following:

(1) The dates and provisions of all previous time extensions on the project; and

(2) A detailed justification for the delay and a projected completion date. The RD shall review the request and make a determination. The Grantee shall be notified of the RD's determination in writing. If the RD approves the request, the letter shall reflect the approved completion date and any other requirements the RD may determine necessary to ensure that the new completion date is met. If the RD denies the time extension request, the grantee may, upon completion of the project, be reimbursed for eligible project costs incurred only up to the latest approved completion date. If the project is not completed, no Federal funding will be provided for that project.

(e) Cost Overruns. (1) During the execution of approved work a subgrantee may find that the actual project costs exceed the approved Project Worksheet estimates. Such cost overruns normally fall into the following three categories:

(i) Variations in unit prices;

(ii) Change in the scope of eligible work; or

(iii) Delays in timely starts or completion of eligible work.

(2) The subgrantee must evaluate each cost overrun and, when justified, submit a request for additional funding through the Grantee to the RD for a final determination. All requests for the RD's approval will contain sufficient documentation to support the eligibility of all claimed work and costs. The Grantee must include a written recommendation when forwarding the request. The RD will notify the Grantee in writing of the final determination. FEMA will not normally review an overrun for an individual small project. The normal procedure for small projects will be that when a subgrantee discovers a significant overrun related to the total final cost for all small projects, the subgrantee may submit an appeal for additional funding in accordance with §206.206, within 60 days following the completion of all its small projects.

(f) Progress reports. Progress reports will be submitted by the Grantee to the RD quarterly. The RD and Grantee shall negotiate the date for submission of the first report. Such reports will describe the status of those projects on which a final payment of the Federal share has not been made to the grantee and outline any problems or circumstances expected to result in noncompliance with the approved grant conditions.

[55 FR 2304, Jan. 23, 1990; 55 FR 5458, Feb. 15, 1990, as amended at 64 FR 55161, Oct. 12, 1999]

§ 206.205   Payment of claims.

(a) Small Projects. Final payment of the Federal share of these projects will be made to the Grantee upon approval of the Project Worksheet. The Grantee will make payment of the Federal share to the subgrantee as soon as practicable after Federal approval of funding. Before the closeout of the disaster contract, the Grantee must certify that all such projects were completed in accordance with FEMA approvals and that the State contribution to the non-Federal share, as specified in the FEMA-State Agreement, has been paid to each subgrantee. Such certification is not required to specify the amount spent by a subgrantee on small projects. The Federal payment for small projects shall not be reduced if all of the approved funds are not spent to complete a project. However, failure to complete a project may require that the Federal payment be refunded.

(b) Large projects. (1) The Grantee shall make an accounting to the RD of eligible costs for each approved large project. In submitting the accounting the Grantee shall certify that reported costs were incurred in the performance of eligible work, that the approved work was completed, that the project is in compliance with the provisions of the FEMA-State Agreement, and that payments for that project have been made in accordance with 44 CFR 13.21, Payments. Each large project shall be submitted as soon as practicable after the subgrantee has completed the approved work and requested payment.

(2) The RD shall review the accounting to determine the eligible amount of reimbursement for each large project and approve eligible costs. If a discrepancy between reported costs and approved funding exists, the RD may conduct field reviews to gather additional information. If discrepancies in the claim cannot be resolved through a field review, a Federal audit may be conducted. If the RD determines that eligible costs exceed the initial approval, he/she will obligate additional funds as necessary.

[55 FR 2304, Jan. 23, 1990, as amended at 64 FR 55161, Oct. 12, 1999]

§ 206.206   Appeals.

An eligible applicant, subgrantee, or grantee may appeal any determination previously made related to an application for or the provision of Federal assistance according to the procedures below.

(a) Format and Content. The applicant or subgrantee will make the appeal in writing through the grantee to the Regional Director. The grantee shall review and evaluate all subgrantee appeals before submission to the Regional Director. The grantee may make grantee-related appeals to the Regional Director. The appeal shall contain documented justification supporting the appellant's position, specifying the monetary figure in dispute and the provisions in Federal law, regulation, or policy with which the appellant believes the initial action was inconsistent.

(b) Levels of Appeal. (1) The Regional Director will consider first appeals for public assistance-related decisions under subparts A through L of this part.

(2) The Associate Director/Executive Associate Director for Response and Recovery will consider appeals of the Regional Director's decision on any first appeal under paragraph (b)(1) of this section.

(c) Time Limits. (1) Appellants must file appeals within 60 days after receipt of a notice of the action that is being appealed.

(2) The grantee will review and forward appeals from an applicant or subgrantee, with a written recommendation, to the Regional Director within 60 days of receipt.

(3) Within 90 days following receipt of an appeal, the Regional Director (for first appeals) or Associate Director/Executive Associate Director (for second appeals) will notify the grantee in writing of the disposition of the appeal or of the need for additional information. A request by the Regional Director or Associate Director/Executive Associate Director for additional information will include a date by which the information must be provided. Within 90 days following the receipt of the requested additional information or following expiration of the period for providing the information, the Regional Director or Associate Director/Executive Associate Director will notify the grantee in writing of the disposition of the appeal. If the decision is to grant the appeal, the Regional Director will take appropriate implementing action.

(d) Technical Advice. In appeals involving highly technical issues, the Regional Director or Associate Director/Executive Associate Director may, at his or her discretion, submit the appeal to an independent scientific or technical person or group having expertise in the subject matter of the appeal for advice or recommendation. The period for this technical review may be in addition to other allotted time periods. Within 90 days of receipt of the report, the Regional Director or Associate Director/Executive Associate Director will notify the grantee in writing of the disposition of the appeal.

(e) Transition. (1) This rule is effective for all appeals pending on and appeals from decisions issued on or after May 8, 1998, except as provided in paragraph (e)(2) of this section.

(2) Appeals pending from a decision of an Associate Director/Executive Associate Director before May 8, 1998 may be appealed to the Director in accordance with 44 CFR 206.440 as it existed before May 8, 1998 (44 CFR, revised as of October 1, 1997).

(3) The decision of the FEMA official at the next higher appeal level shall be the final administrative decision of FEMA.

[63 FR 17110, Apr. 8, 1998; 63 FR 24970, May 6, 1998]

§ 206.207   Administrative and audit requirements.

(a) General. Uniform administrative requirements which are set forth in 44 CFR part 13 apply to all disaster assistance grants and subgrants.

(b) State administrative plan. (1) The State shall develop a plan for the administration of the Public Assistance program that includes at a minimum, the items listed below:

(i) The designation of the State agency or agencies which will have the responsibility for program administration.

(ii) The identification of staffing functions in the Public Assistance program, the sources of staff to fill these functions, and the management and oversight responsibilities of each.

(iii) Procedures for:

(A) Notifying potential applicants of the availability of the program;

(B) Conducting briefings for potential applicants and application procedures, program eligibility guidance and program deadlines;

(C) Assisting FEMA in determining applicant eligibility;

(D) Participating with FEMA in conducting damage surveys to serve as a basis for obligations of funds to subgrantees;

(E) Participating with FEMA in the establishment of hazard mitigation and insurance requirements;

(F) Processing appeal requests, requests for time extensions and requests for approval of overruns, and for processing appeals of grantee decisions;

(G) Compliance with the administrative requirements of 44 CFR parts 13 and 206;

(H) Compliance with the audit requirements of 44 CFR part 14;

(I) Processing requests for advances of funds and reimbursement; and

(J) Determining staffing and budgeting requirements necessary for proper program management.

(2) The Grantee may request the RD to provide technical assistance in the preparation of such administrative plan.

(3) In accordance with the Interim Rule published March 21, 1989, the Grantee was to have submitted an administrative plan to the RD for approval by September 18, 1989. An approved plan must be on file with FEMA before grants will be approved in a future major disaster. Thereafter, the Grantee shall submit a revised plan to the RD annually. In each disaster for which Public Assistance is included, the RD shall request the Grantee to prepare any amendments required to meet current policy guidance.

(4) The Grantee shall ensure that the approved administrative plan is incorporated into the State emergency plan.

(c) Audit—(1) Nonfederal audit. For grantees or subgrantees, requirements for nonfederal audit are contained in FEMA regulations at 44 CFR part 14 or OMB Circular A–110 as appropriate.

(2) Federal audit. In accordance with 44 CFR part 14, appendix A, para. 10, FEMA may elect to conduct a Federal audit of the disaster assistance grant or any of the subgrants.

[55 FR 2304, Jan. 23, 1990; 55 FR 5458, Feb. 15, 1990]

§ 206.208   Direct Federal assistance.

(a) General. When the State and local government lack the capability to perform or to contract for eligible emergency work and/or debris removal, under sections 402(4), 403 or 407 of the Act, the Grantee may request that the work be accomplished by a Federal agency. Such assistance is subject to the cost sharing provisions outlined in §206.203(b) of this subpart. Direct Federal assistance is also subject to the eligibility criteria contained in Subpart H of these regulations. FEMA will reimburse other Federal agencies in accordance with Subpart A of these regulations.

(b) Requests for assistance. All requests for direct Federal assistance shall be submitted by the Grantee to the RD and shall include:

(1) A written agreement that the State will:

(i) Provide without cost to the United States all lands, easements and rights-of-ways necessary to accomplish the approved work;

(ii) Hold and save the United States free from damages due to the requested work, and shall indemnify the Federal Government against any claims arising from such work;

(iii) Provide reimbursement to FEMA for the nonFederal share of the cost of such work in accordance with the provisions of the FEMA-State Agreement; and

(iv) Assist the performing Federal agency in all support and local jurisdictional matters.

(2) A statement as to the reasons the State and the local government cannot perform or contract for performance of the requested work.

(3) A written agreement from an eligible applicant that such applicant will be responsible for the items in subparagraph (b)(1) (i) and (ii) of this section, in the event that a State is legally unable to provide the written agreement.

(c) Implementation. (1) If the RD approves the request, a mission assignment will be issued to the appropriate Federal agency. The mission assignment letter to the agency will define the scope of eligible work, the estimated cost of the eligible work and the billing period frequency. The Federal agency must not exceed the approved funding limit without the authorization of the RD.

(2) If all or any part of the requested work falls within the statutory authority of another Federal agency, the RD shall not approve that portion of the work. In such case, the unapproved portion of the request will be referred to the appropriate agency for action.

(d) Time limitation. The time limitation for completion of work by a Federal agency under a mission assignment is 60 days after the President's declaration. Based on extenuating circumstances or unusual project requirements, the RD may extend this time limitation.

(e) Project management. (1) The performing Federal agency shall ensure that the work is completed in accordance with the RD's approved scope of work, costs and time limitations. The performing Federal agency shall also keep the RD and Grantee advised of work progress and other project developments. It is the responsibility of the performing Federal agency to ensure compliance with applicable Federal, State and local legal requirements. A final inspection report will be completed upon termination of all direct Federal assistance work. Final inspection reports shall be signed by a representative of the performing Federal agency and the State. Once the final eligible cost is determined (including Federal agency overhead), the State will be billed for the nonFederal share of the mission assignment in accordance with the cost sharing provisions of the FEMA-State Agreement.

(2) Pursuant to the agreements provided in the request for assistance the Grantee shall assist the performing Federal agency in all State and local jurisdictional matters. These matters include securing local building permits and rights of entry, control of traffic and pedestrians, and compliance with local building ordinances.

[55 FR 2304, Jan. 23, 1990, as amended at 64 FR 55161, Oct. 12, 1999]

§§ 206.209-206.219   [Reserved]