47 C.F.R. Subpart I—Procedures Implementing the National Environmental Policy Act of 1969
Title 47 - Telecommunication
Source: 51 FR 15000, Apr. 22, 1986, unless otherwise noted.
The provisions of this subpart implement Subchapter I of the National Environmental Policy Act of 1969, as amended, 42 U.S.C. 4321–4335. A further explanation regarding implementation of the National Environmental Policy Act is provided by the regulations issued by the Council on Environmental Quality, 40 CFR 1500–1508.28. The provisions of this subpart shall apply to all Commission actions that may or will have a significant impact on the quality of the human environment. To the extent that other provisions of the Commission's rules and regulations are inconsistent with the subpart, the provisions of this subpart shall govern. [55 FR 20396, May 16, 1990] For general information and assistance concerning the provisions of this subpart, the Office of General Counsel may be contacted, (202) 632–6990. For more specific information, the Bureau responsible for processing a specific application should be contacted. Any Commission action deemed to have a significant effect upon the quality of the human environment requires the preparation of a Draft Environmental Impact Statement (DEIS) and Final Environmental Impact Statement (FEIS) (collectively referred to as EISs) (see §§1.1314, 1.1315 and 1.1317). The Commission has reviewed representative actions and has found no common pattern which would enable it to specify actions that will thus automatically require EISs. Note: Our current application forms refer applicants to §1.1305 to determine if their proposals are such that the submission of environmental information is required (see §1.1311). Until the application forms are revised to reflect our new environmental rules, applicants should refer to §1.1307. Section 1.1307 now delineates those actions for which applicants must submit environmental information.
Title 47: Telecommunication
PART 1—PRACTICE AND PROCEDURE
Subpart I—Procedures Implementing the National Environmental Policy Act of 1969
§ 1.1301 Basis and purpose.
§ 1.1302 Cross-reference; Regulations of the Council on Environmental Quality.
§ 1.1303 Scope.
§ 1.1304 Information and assistance.
§ 1.1305 Actions which normally will have a significant impact upon the environment, for which Environmental Impact Statements must be prepared.
§ 1.1306 Actions which are categorically excluded from environmental processing.
(a) Except as provided in §1.1307 (c) and (d), Commission actions not covered by §1.1307 (a) and (b) are deemed individually and cumulatively to have no significant effect on the quality of the human environment and are categorically excluded from environmental processing.
(b) Specifically, any Commission action with respect to any new application, or minor or major modifications of existing or authorized facilities or equipment, will be categorically excluded, provided such proposals do not:
(1) Involve a site location specified under §1.1307(a) (1)–(7), or
(2) Involve high intensity lighting under §1.1307(a)(8).
(3) Result in human exposure to radiofrequency radiation in excess of the applicable safety standards specified in §1.1307(b).
Note 1: The provisions of §1.1307(a) of this part requiring the preparation of EAs do not encompass the mounting of antenna(s) on an existing building or antenna tower unless §1.1307(a)(4) of this part is applicable. Such antennas are subject to §1.1307(b) of this part and require EAs if their construction would result in human exposure to radiofrequency radiation in excess of the applicable health and safety guidelines cited in §1.1307(b) of this part. The provisions of §1.1307 (a) and (b) of this part do not encompass the installation of aerial wire or cable over existing aerial corridors of prior or permitted use or the underground installation of wire or cable along existing underground corridors of prior or permitted use, established by the applicant or others. The use of existing buildings, towers or corridors is an environmentally desirable alternative to the construction of new facilities and is encouraged. The provisions of §1.1307(a) and (b) of this part do not encompass the construction of new submarine cable systems.
Note 2: The specific height of an antenna tower or supporting structure, as well as the specific diameter of a satellite earth station, in and of itself, will not be deemed sufficient to warrant environmental processing, see §§1.1307 and 1.1308.
Note 3: The construction of an antenna tower or supporting structure in an established “antenna farm”: (i.e., an area in which similar antenna towers are clustered, whether or not such area has been officially designated as an antenna farm), will be categorically excluded unless one or more of the antennas to be mounted on the tower or structure are subject to the provisions of §1.1307(b) and the additional radiofrequency radiation from the antenna(s) on the new tower or structure would cause human exposure in excess of the applicable health and safety guidelines cited in §1.1307(b).
[51 FR 15000, Apr. 22, 1986, as amended at 51 FR 18889, May 23, 1986; 53 FR 28393, July 28, 1988; 56 FR 13414, Apr. 2, 1991; 64 FR 19061, Apr. 19, 1999]
§ 1.1307 Actions that may have a significant environmental effect, for which Environmental Assessments (EAs) must be prepared.
(a) Commission actions with respect to the following types of facilities may significantly affect the environment and thus require the preparation of EAs by the applicant (see §§1.1308 and 1.1311) and may require further Commission environmental processing (see §§1.1314, 1.1315 and 1.1317):
(1) Facilities that are to be located in an officially designated wilderness area.
(2) Facilities that are to be located in an officially designated wildlife preserve.
(3) Facilities that: (i) May affect listed threatened or endangered species or designated critical habitats; or (ii) are likely to jeopardize the continued existence of any proposed endangered or threatened species or likely to result in the destruction or adverse modification of proposed critical habitats, as determined by the Secretary of the Interior pursuant to the Endangered Species Act of 1973.
Note: The list of endangered and threatened species is contained in 50 CFR 17.11, 17.22, 222.23(a) and 227.4. The list of designated critical habitats is contained in 50 CFR 17.95, 17.96 and part 226. To ascertain the status of proposed species and habitats, inquiries may be directed to the Regional Director of the Fish and Wildlife Service, Department of the Interior.
(4) Facilities that may affect districts, sites, buildings, structures or objects, significant in American history, architecture, archeology, engineering or culture, that are listed, or are eligible for listing, in the National Register of Historic Places. (See 16 U.S.C. 470w(5); 36 CFR part 60 and 800.) To ascertain whether a proposed action may affect properties that are listed or eligible for listing in the National Register of Historic Places, an applicant shall follow the procedures set forth in the rules of the Advisory Council on Historic Preservation, 36 CFR part 800, as modified and supplemented by the Nationwide Programmatic Agreement for the Collocation of Wireless Antennas, Appendix B to Part 1 of this Chapter, and the Nationwide Programmatic Agreement Regarding the Section 106 National Historic Preservation Act Review Process, Appendix C to Part 1 of this Chapter.
(5) Facilities that may affect Indian religious sites.
(6) Facilities to be located in a flood Plain (See Executive Order 11988.)
(7) Facilities whose construction will involve significant change in surface features (e.g., wetland fill, deforestation or water diversion). (In the case of wetlands on Federal property, see Executive Order 11990.)
(8) Antenna towers and/or supporting structures that are to be equipped with high intensity white lights which are to be located in residential neighborhoods, as defined by the applicable zoning law.
(b) In addition to the actions listed in paragraph (a) of this section, Commission actions granting construction permits, licenses to transmit or renewals thereof, equipment authorizations or modifications in existing facilities, require the preparation of an Environmental Assessment (EA) if the particular facility, operation or transmitter would cause human exposure to levels of radiofrequency radiation in excess of the limits in §§1.1310 and 2.1093 of this chapter. Applications to the Commission for construction permits, licenses to transmit or renewals thereof, equipment authorizations or modifications in existing facilities must contain a statement confirming compliance with the limits unless the facility, operation, or transmitter is categorically excluded, as discussed below. Technical information showing the basis for this statement must be submitted to the Commission upon request. Such compliance statements may be omitted from license applications for transceivers subject to the certification requirement in §25.129 of this chapter.
(1) The appropriate exposure limits in §§1.1310 and 2.1093 of this chapter are generally applicable to all facilities, operations and transmitters regulated by the Commission. However, a determination of compliance with the exposure limits in §1.1310 or §2.1093 of this chapter (routine environmental evaluation), and preparation of an EA if the limits are exceeded, is necessary only for facilities, operations and transmitters that fall into the categories listed in table 1, or those specified in paragraph (b)(2) of this section. All other facilities, operations and transmitters are categorically excluded from making such studies or preparing an EA, except as indicated in paragraphs (c) and (d) of this section. For purposes of table 1, building-mounted antennas means antennas mounted in or on a building structure that is occupied as a workplace or residence. The term power in column 2 of table 1 refers to total operating power of the transmitting operation in question in terms of effective radiated power (ERP), equivalent isotropically radiated power (EIRP), or peak envelope power (PEP), as defined in §2.1 of this chapter. For the case of the Cellular Radiotelephone Service, subpart H of part 22 of this chapter; the Personal Communications Service, part 24 of this chapter and the Specialized Mobile Radio Service, part 90 of this chapter, the phrase total power of all channels in column 2 of table 1 means the sum of the ERP or EIRP of all co-located simultaneously operating transmitters owned and operated by a single licensee. When applying the criteria of table 1, radiation in all directions should be considered. For the case of transmitting facilities using sectorized transmitting antennas, applicants and licensees should apply the criteria to all transmitting channels in a given sector, noting that for a highly directional antenna there is relatively little contribution to ERP or EIRP summation for other directions.
Table 1_Transmitters, Facilities and Operations Subject to Routine Environmental Evaluation------------------------------------------------------------------------ Service (title 47 CFR rule part) Evaluation required if:------------------------------------------------------------------------Experimental Radio Services (part 5)... Power > 100 W ERP (164 W EIRP).Paging and Radiotelephone Service Non-building-mounted antennas: (subpart E of part 22). height above ground level to lowest point of antenna < 10 m and power > 1000 W ERP (1640 W EIRP). Building-mounted antennas: power > 1000 W ERP (1640 W EIRP).Cellular Radiotelephone Service Non-building-mounted antennas: (subpart H of part 22). height above ground level to lowest point of antenna < 10 m and total power of all channels > 1000 W ERP (1640 W EIRP). Building-mounted antennas: total power of all channels > 1000 W ERP (1640 W EIRP).Personal Communications Services (part (1) Narrowband PCS (subpart D): 24). Non-building-mounted antennas: height above ground level to lowest point of antenna < 10 m and total power of all channels > 1000 W ERP (1640 W EIRP). Building-mounted antennas: total power of all channels > 1000 W ERP (1640 W EIRP). (2) Broadband PCS (subpart E): Non-building-mounted antennas: height above ground level to lowest point of antenna < 10 m and total power of all channels > 2000 W ERP (3280 W EIRP). Building-mounted antennas: total power of all channels > 2000 W ERP (3280 W EIRP).Satellite Communications Services (part All included. 25). In addition, for NGSO subscriber equipment, licensees are required to attach a label to subscriber transceiver antennas that: (1) provides adequate notice regarding potential radiofrequency safety hazards, e.g., information regarding the safe minimum separation distance required between users and transceiver antennas; and (2) references the applicable FCC-adopted limits for radiofrequency exposure specified in § 1.1310 of this chapter.Miscellaneous Wireless Communications (1) For the 1390-1392 MHz, 1392- Services (part 27 except subpart M). 1395 MHz, 1432-1435 MHz, 1670- 1675 MHz, and 2385-2390 MHz bands: Non-building-mounted antennas: height above ground level to lowest point of antenna < 10 m and total power of all channels > 2000 W ERP (3280 W EIRP). Building-mounted antennas: total power of all channels > 2000 W ERP (3280 W EIRP). (2) For the 698-746 MHz, 746- 764 MHz, 776-794 MHz, 2305- 2320 MHz, and 2345-2360 MHz bands: Total power of all channels > 1000 W ERP (1640 W EIRP).Broadband Radio Service and Educational Non-building-mounted antennas: Broadband Service (subpart M of part height above ground level to 27). lowest point of antenna < 10 m and power > 1640 W EIRP. Building-mounted antennas: power > 1640 W EIRP. BRS and EBS licensees are required to attach a label to subscriber transceiver or transverter antennas that: (1) provides adequate notice regarding potential radiofrequency safety hazards, e.g., information regarding the safe minimum separation distance required between users and transceiver antennas; and (2) references the applicable FCC-adopted limits for radiofrequency exposure specified in § 1.1310.Radio Broadcast Services (part 73)..... All included.Experimental Radio, Auxiliary, Special Subparts A, G, L: power > Broadcast and Other Program 100 W ERP. Distributional Services (part 74).Stations in the Maritime Services (part Ship earth stations only. 80).Private Land Mobile Radio Services Non-building-mounted antennas: Paging Operations (subpart P of part height above ground level to 90). lowest point of antenna < 10 m and power > 1000 W ERP (1640 W EIRP). Building-mounted antennas: power > 1000 W ERP (1640 W EIRP).Private Land Mobile Radio Services Non-building-mounted antennas: Specialized Mobile Radio (subpart S of height above ground level to part 90). lowest point of antenna < 10 m and total power of all channels > 1000 W ERP (1640 W EIRP). Building-mounted antennas: Total power of all channels > 1000 W ERP (1640 W EIRP).Amateur Radio Service (part 97)........ Transmitter output power > levels specified in § 97.13(c)(1) of this chapter.Local Multipoint Distribution Service Non-building-mounted antennas: (subpart L of part 101) and 24 GHz height above ground level to (subpart G of part 101). lowest point of antenna < 10 m and power > 1640 W EIRP. Building-mounted antennas: power > 1640 W EIRP. LMDS and 24 GHz Service licensees are required to attach a label to subscriber transceiver antennas that: (1) provides adequate notice regarding potential radiofrequency safety hazards, e.g., information regarding the safe minimum separation distance required between users and transceiver antennas; and (2) references the applicable FCC-adopted limits for radiofrequency exposure specified in § 1.1310.70/80/90 GHz Bands (subpart Q of part Non-building-mounted antennas: 101). height above ground level to lowest point of antenna < 10 m and power > 1640 W EIRP. Building-mounted antennas: power > 1640 W EIRP. Licensees are required to attach a label to transceiver antennas that: (1) provides adequate notice regarding potential radiofrequency safety hazards, e.g., information regarding the safe minimum separation distance required between users and transceiver antennas; and (2) references the applicable FCC-adopted limits for radiofrequency exposure specified in § 1.1310.------------------------------------------------------------------------
|
(2) Mobile and portable transmitting devices that operate in the Cellular Radiotelephone Service, the Personal Communications Services (PCS), the Satellite Communications Services, the Wireless Communications Service, the Maritime Services (ship earth stations only), the Specialized Mobile Radio Service, and the 3650MHz Wireless Broadband Service authorized under Subpart H of parts 22, 24, 25, 27, 80, and 90 of this chapter are subject to routine environmental evaluation for RF exposure prior to equipment authorization or use, as specified in §§2.1091 and 2.1093 of this chapter. Unlicensed PCS, unlicensed NII and millimeter wave devices are also subject to routine environmental evaluation for RF exposure prior to equipment authorization or use, as specified in §§15.253(f), 15.255(g), 15.319(i), and 15.407(f) of this chapter. Portable transmitting equipment for use in the Wireless Medical Telemetry Service (WMTS) is subject to routine environment evaluation as specified in §§2.1093 and 5.1125 of this chapter. Equipment authorized for use in the Medical Implant Communications Service (MICS) as a medical implant transmitter (as defined in Appendix 1 to Subpart E of part 95 of this chapter) is subject to routine environmental evaluation for RF exposure prior to equipment authorization, as specified in §2.1093 of this chapter by finite difference time domain computational modeling or laboratory measurement techniques. Where a showing is based on computational modeling, the Commission retains the discretion to request that specific absorption rate measurement data be submitted. All other mobile, portable, and unlicensed transmitting devices are categorically excluded from routine environmental evaluation for RF exposure under §§2.1091, 2.1093 of this chapter except as specified in paragraphs (c) and (d) of this section. (3) In general, when the guidelines specified in §1.1310 are exceeded in an accessible area due to the emissions from multiple fixed transmitters, actions necessary to bring the area into compliance are the shared responsibility of all licensees whose transmitters produce, at the area in question, power density levels that exceed 5% of the power density exposure limit applicable to their particular transmitter or field strength levels that, when squared, exceed 5% of the square of the electric or magnetic field strength limit applicable to their particular transmitter. Owners of transmitter sites are expected to allow applicants and licensees to take reasonable steps to comply with the requirements contained in §1.1307(b) and, where feasible, should encourage co-location of transmitters and common solutions for controlling access to areas where the RF exposure limits contained in §1.1310 might be exceeded. (i) Applicants for proposed (not otherwise excluded) transmitters, facilities or modifications that would cause non-compliance with the limits specified in §1.1310 at an accessible area previously in compliance must submit an EA if emissions from the applicant's transmitter or facility would result, at the area in question, in a power density that exceeds 5% of the power density exposure limit applicable to that transmitter or facility or in a field strength that, when squared, exceeds 5% of the square of the electric or magnetic field strength limit applicable to that transmitter or facility. (ii) Renewal applicants whose (not otherwise excluded) transmitters or facilities contribute to the field strength or power density at an accessible area not in compliance with the limits specified in §1.1310 must submit an EA if emissions from the applicant's transmitter or facility results, at the area in question, in a power density that exceeds 5% of the power density exposure limit applicable to that transmitter or facility or in a field strength that, when squared, exceeds 5% of the square of the electric or magnetic field strength limit applicable to that transmitter of facility. (4) Transition Provisions. Applications filed with the Commission prior to October 15, 1997 (or January 1, 1998, for the Amateur Radio Service only), for construction permits, licenses to transmit or renewals thereof, modifications in existing facilities or other authorizations or renewals thereof require the preparation of an Environmental Assessment if the particular facility, operation or transmitter would cause human exposure to levels of radiofrequency radiation that are in excess of the requirements contained in paragraphs (b)(4)(i) through (b)(4)(iii) of this section. In accordance with §1.1312, if no new application or Commission action is required for a licensee to construct a new facility or physically modify an existing facility, e.g., geographic area licensees, and construction begins on or after October 15, 1997, the licensee will be required to prepare an Environmental Assessment if construction or modification of the facility would not comply with the provisions of paragraph (b)(1) of this section. These transition provisions do not apply to applications for equipment authorization or use for mobile, portable and unlicensed devices as specified in paragraph (b)(2) of this section. (i) For facilities and operations licensed or authorized under parts 5, 21 (subpart K), 25, 73, 74 (subparts A, G, I, and L), and 80 of this chapter, the “Radio Frequency Protection Guides” recommended in “American National Standard Safety Levels with Respect to Human Exposure to Radio Frequency Electromagnetic Fields, 300 kHz to 100 GHz”, (ANSI C95.1–1982), issued by the American National Standards Institute (ANSI) and copyright 1982 by the Institute of Electrical and Electronics Engineers, Inc., New York, New York shall apply. With respect to subpart K of part 21 and subpart I of part 74 of this chapter, these requirements apply only to multipoint distribution service and instructional television fixed service stations transmitting with an equivalent isotropically radiated power (EIRP) in excess of 200 watts. With respect to subpart L of part 74 of this chapter, these requirements apply only to FM booster and translator stations transmitting with an effective radiated power (ERP) in excess of 100 watts. With respect to part 80 of this chapter, these requirements apply only to ship earth stations. (ii) For facilities and operations licensed or authorized under part 24 of this chapter, licensees and manufacturers are required to ensure that their facilities and equipment comply with IEEE C95.1–1991 (ANSI/IEEE C95.1–1992), “Safety Levels With Respect to Human Exposure to Radio Frequency Electromagnetic Fields, 3 kHz to 300 GHz.” Measurement methods are specified in IEEE C95.3–1991, “Recommended Practice for the Measurement of Potentially Hazardous Electromagnetic Fields—RF and Microwave.” Copies of these standards are available from IEEE Standards Board, 445 Hoes Lane, P.O. Box 1331, Piscataway, NJ 08855–1331. Telephone: 1–800–678–4333. The limits for both “controlled” and “uncontrolled” environments, as defined by IEEE C95.1–1991, will apply to all PCS base and mobile stations, as appropriate. (iii) Applications for all other types of facilities and operations are categorically excluded from routine RF radiation evaluation except as provided in paragraphs (c) and (d) of this section. (5) Existing transmitting facilities, devices and operations: All existing transmitting facilities, operations and devices regulated by the Commission must be in compliance with the requirements of paragraphs (b)(1) through (b)(3) of this section by September 1, 2000, or, if not in compliance, file an Environmental Assessment as specified in §1.1311. (c) If an interested person alleges that a particular action, otherwise categorically excluded, will have a significant environmental effect, the person shall submit to the Bureau responsible for processing that action a written petition setting forth in detail the reasons justifying or circumstances necessitating environmental consideration in the decision-making process. (See §1.1313). The Bureau shall review the petition and consider the environmental concerns that have been raised. If the Bureau determines that the action may have a significant environmental impact, the Bureau will require the applicant to prepare an EA (see §§1.1308 and 1.1311), which will serve as the basis for the determination to proceed with or terminate environmental processing. (d) If the Bureau responsible for processing a particular action, otherwise categorically excluded, determines that the proposal may have a significant environmental impact, the Bureau, on its own motion, shall require the applicant to submit an EA. The Bureau will review and consider the EA as in paragraph (c) of this section. (e) No State or local government or instrumentality thereof may regulate the placement, construction, and modification of personal wireless service facilities on the basis of the environmental effects of radio frequency emissions to the extent that such facilities comply with the regulations contained in this chapter concerning the environmental effects of such emissions. For purposes of this paragraph: (1) The term personal wireless service means commercial mobile services, unlicensed wireless services, and common carrier wireless exchange access services; (2) The term personal wireless service facilities means facilities for the provision of personal wireless services; (3) The term unlicensed wireless services means the offering of telecommunications services using duly authorized devices which do not require individual licenses, but does not mean the provision of direct-to-home satellite services; and (4) The term direct-to-home satellite services means the distribution or broadcasting of programming or services by satellite directly to the subscriber's premises without the use of ground receiving or distribution equipment, except at the subscriber's premises or in the uplink process to the satellite. [51 FR 15000, Apr. 22, 1986] Editorial Note: For § 1.1308 Consideration of environmental assessments (EAs); findings of no significant impact.(a) Applicants shall prepare EAs for actions that may have a significant environmental impact (see §1.1307). An EA is described in detail in §1.1311 of this part of the Commission rules. (b) The EA is a document which shall explain the environmental consequences of the proposal and set forth sufficient analysis for the Bureau or the Commission to reach a determination that the proposal will or will not have a significant environmental effect. To assist in making that determination, the Bureau or the Commission may request further information from the applicant, interested persons, and agencies and authorities which have jurisdiction by law or which have relevant expertise. Note: With respect to actions specified under §1.1307 (a)(3) and (a)(4), the Commission shall solicit and consider the comments of the Department of Interior, and the State Historic Preservation Officer and the Advisory Council on Historic Preservation, respectively, in accordance with their established procedures. See Interagency Cooperation—Endangered Species Act of 1973, as amended, 50 CFR part 402; Protection of Historic and Cultural Properties, 36 CFR part 800. In addition, when an action interferes with or adversely affects an American Indian tribe's religious site, the Commission shall solicit the views of that American Indian tribe. See §1.1307(a)(5). (c) If the Bureau or the Commission determines, based on an independent review of the EA and any applicable mandatory consultation requirements imposed upon Federal agencies (see note above), that the proposal will have a significant environmental impact upon the quality of the human environment, it will so inform the applicant. The applicant will then have an opportunity to amend its application so as to reduce, minimize, or eliminate environmental problems. See §1.1309. If the environmental problem is not eliminated, the Bureau will publish in the (d) If the Bureau or Commission determines, based on an independent review of the EA, and any mandatory consultation requirements imposed upon Federal agencies (see the note to paragraph (b) of this section), that the proposal would not have a significant impact, it will make a finding of no significant impact. Thereafter, the application will be processed without further documentation of environmental effect. Pursuant to CEQ regulations, see 40 CFR 1501.4 and 1501.6, the applicant must provide the community notice of the Commission's finding of no significant impact. [51 FR 15000, Apr. 22, 1986; 51 FR 18889, May 23, 1986, as amended at 53 FR 28394, July 28, 1988] § 1.1309 Application amendments.Applicants are permitted to amend their applications to reduce, minimize or eliminate potential environmental problems. As a routine matter, an applicant will be permitted to amend its application within thirty (30) days after the Commission or the Bureau informs the applicant that the proposal will have a significant impact upon the quality of the human environment (see §1.1308(c)). The period of thirty (30) days may be extended upon a showing of good cause. § 1.1310 Radiofrequency radiation exposure limits.The criteria listed in table 1 shall be used to evaluate the environmental impact of human exposure to radiofrequency (RF) radiation as specified in §1.1307(b), except in the case of portable devices which shall be evaluated according to the provisions of §2.1093 of this chapter. Further information on evaluating compliance with these limits can be found in the FCC's OST/OET Bulletin Number 65, “Evaluating Compliance with FCC-Specified Guidelines for Human Exposure to Radiofrequency Radiation.” Note to Introductory Paragraph: These limits are generally based on recommended exposure guidelines published by the National Council on Radiation Protection and Measurements (NCRP) in “Biological Effects and Exposure Criteria for Radiofrequency Electromagnetic Fields,” NCRP Report No. 86, Sections 17.4.1, 17.4.1.1, 17.4.2 and 17.4.3. Copyright NCRP, 1986, Bethesda, Maryland 20814. In the frequency range from 100 MHz to 1500 MHz, exposure limits for field strength and power density are also generally based on guidelines recommended by the American National Standards Institute (ANSI) in Section 4.1 of “IEEE Standard for Safety Levels with Respect to Human Exposure to Radio Frequency Electromagnetic Fields, 3 kHz to 300 GHz,” ANSI/IEEE C95.1–1992, Copyright 1992 by the Institute of Electrical and Electronics Engineers, Inc., New York, New York 10017. |
Table 1_Limits for Maximum Permissible Exposure (MPE)---------------------------------------------------------------------------------------------------------------- Electric field Magnetic field Power density Averaging time Frequency range (MHz) strength (V/m) strength (A/m) (mW/cm\2\) (minutes)---------------------------------------------------------------------------------------------------------------- (A) Limits for Occupational/Controlled Exposures----------------------------------------------------------------------------------------------------------------0.3-3.0............................. 614 1.63 *(100) 63.0-30.............................. 1842/f 4.89/f *(900/f\2\) 630-300.............................. 61.4 0.163 1.0 6300-1500............................ ................. ................. f/300 61500-100,000........................ ................. ................. 5 6---------------------------------------------------------------------------------------------------------------- (B) Limits for General Population/Uncontrolled Exposure----------------------------------------------------------------------------------------------------------------0.3-1.34............................ 614 1.63 *(100) 301.34-30............................. 824/f 2.19/f *(180/f\2\) 3030-300.............................. 27.5 0.073 0.2 30300-1500............................ ................. ................. f/1500 301500-100,000........................ ................. ................. 1.0 30----------------------------------------------------------------------------------------------------------------f = frequency in MHz* = Plane-wave equivalent power densityNote 1 to Table 1: Occupational/controlled limits apply in situations in which persons are exposed as a consequence of their employment provided those persons are fully aware of the potential for exposure and can exercise control over their exposure. Limits for occupational/controlled exposure also apply in situations when an individual is transient through a location where occupational/controlled limits apply provided he or she is made aware of the potential for exposure.Note 2 to Table 1: General population/uncontrolled exposures apply in situations in which the general public may be exposed, or in which persons that are exposed as a consequence of their employment may not be fully aware of the potential for exposure or can not exercise control over their exposure.
|
[61 FR 41016, Aug. 7, 1996] § 1.1311 Environmental information to be included in the environmental assessment (EA).(a) The applicant shall submit an EA with each application that is subject to environmental processing (see §1.1307). The EA shall contain the following information: (1) For antenna towers and satellite earth stations, a description of the facilities as well as supporting structures and appurtenances, and a description of the site as well as the surrounding area and uses. If high intensity white lighting is proposed or utilized within a residential area, the EA must also address the impact of this lighting upon the residents. (2) A statement as to the zoning classification of the site, and communications with, or proceedings before and determinations (if any) made by zoning, planning, environmental or other local, state or Federal authorities on matters relating to environmental effect. (3) A statement as to whether construction of the facilities has been a source of controversy on environmental grounds in the local community. (4) A discussion of environmental and other considerations which led to the selection of the particular site and, if relevant, the particular facility; the nature and extent of any unavoidable adverse environmental effects, and any alternative sites or facilities which have been or might reasonably be considered. (5) Any other information that may be requested by the Bureau or Commission. (6) If endangered or threatened species or their critical habitats may be affected, the applicant's analysis must utilize the best scientific and commercial data available, see 50 CFR 402.14(c). (b) The information submitted in the EA shall be factual (not argumentative or conclusory) and concise with sufficient detail to explain the environmental consequences and to enable the Commission or Bureau, after an independent review of the EA, to reach a determination concerning the proposal's environmental impact, if any. The EA shall deal specifically with any feature of the site which has special environmental significance (e.g., wilderness areas, wildlife preserves, natural migration paths for birds and other wildlife, and sites of historic, architectural, or archeological value). In the case of historically significant sites, it shall specify the effect of the facilities on any district, site, building, structure or object listed, or eligible for listing, in the National Register of Historic Places. It shall also detail any substantial change in the character of the land utilized (e.g., deforestation, water diversion, wetland fill, or other extensive change of surface features). In the case of wilderness areas, wildlife preserves, or other like areas, the statement shall discuss the effect of any continuing pattern of human intrusion into the area (e.g., necessitated by the operation and maintenance of the facilities). (c) The EA shall also be accompanied with evidence of site approval which has been obtained from local or Federal land use authorities. (d) To the extent that such information is submitted in another part of the application, it need not be duplicated in the EA, but adequate cross-reference to such information shall be supplied. (e) An EA need not be submitted to the Commission if another agency of the Federal Government has assumed responsibility for determining whether of the facilities in question will have a significant effect on the quality of the human environment and, if it will, for invoking the environmental impact statement process. [51 FR 15000, Apr. 22, 1986, as amended at 51 FR 18889, May 23, 1986; 53 FR 28394, July 28, 1988] § 1.1312 Facilities for which no preconstruction authorization is required.(a) In the case of facilities for which no Commission authorization prior to construction is required by the Commission's rules and regulations the licensee or applicant shall initially ascertain whether the proposed facility may have a significant environmental impact as defined in §1.1307 of this part or is categorically excluded from environmental processing under §1.1306 of this part. (b) If a facility covered by paragraph (a) of this section may have a significant environmental impact, the information required by §1.1311 of this part shall be submitted by the licensee or applicant and ruled on by the Commission, and environmental processing (if invoked) shall be completed, see §1.1308 of this part, prior to the initiation of construction of the facility. (c) If a facility covered by paragraph (a) of this section is categorically excluded from environmental processing, the licensee or applicant may proceed with construction and operation of the facility in accordance with the applicable licensing rules and procedures. (d) If, following the initiation of construction under this section, the licensee or applicant discovers that the proposed facility may have a significant environmental effect, it shall immediately cease construction which may have that effect, and submit the information required by §1.1311 of this part. The Commission shall rule on that submission and complete further environmental processing (if invoked), see §1.1308 of this part, before such construction is resumed. (e) Paragraphs (a) through (d) of this section shall not apply to the construction of mobile stations. [55 FR 20396, May 16, 1990, as amended at 56 FR 13414, Apr. 2, 1991] § 1.1313 Objections.(a) In the case of an application to which section 309(b) of the Communications Act applies, objections based on environmental considerations shall be filed as petitions to deny. (b) Informal objections which are based on environmental considerations must be filed prior to grant of the construction permit, or prior to authorization for facilities that do not require construction permits, or pursuant to the applicable rules governing services subject to lotteries. § 1.1314 Environmental impact statements (EISs).(a) Draft Environmental Impact Statements (DEISs) (§1.1315) and Final Environmental Impact Statements (FEISs) (referred to collectively as EISs) (§1.1317) shall be prepared by the Bureau responsible for processing the proposal when the Commission's or the Bureau's analysis of the EA (§1.1308) indicates that the proposal will have a significant effect upon the environment and the matter has not been resolved by an amendment. (b) As soon as practically feasible, the Bureau will publish in the (c) The EISs shall not address non-environmental considerations. To safeguard against repetitive and unnecessarily lengthy documents, the Statements, where feasible, shall incorporate by reference material set forth in previous documents, with only a brief summary of its content. In preparing the EISs, the Bureau will identify and address the significant environmental issues and eliminate the insignificant issues from analysis. (d) To assist in the preparation of the EISs, the Bureau may request further information from the applicant, interested persons and agencies and authorities, which have jurisdiction by law or which have relevant expertise. The Bureau may direct that technical studies be made by the applicant and that the applicant obtain expert opinion concerning the potential environmental problems and costs associated with the proposed action, as well as comparative analyses of alternatives. The Bureau may also consult experts in an effort to identify measures that could be taken to minimize the adverse effects and alternatives to the proposed facilities that are not, or are less, objectionable. The Bureau may also direct that objections be raised with appropriate local, state or Federal land use agencies or authorities (if their views have not been previously sought). (e) The Bureau responsible for processing the particular application and, thus, preparing the EISs shall draft supplements to Statements where significant new circumstances occur or information arises relevant to environmental concerns and bearing upon the application. (f) The Application, the EA, the DEIS, and the FEIS and all related documents, including the comments filed by the public and any agency, shall be part of the administrative record and will be routinely available for public inspection. (g) If EISs are to be prepared, the applicant must provide the community with notice of the availability of environmental documents and the scheduling of any Commission hearings in that action. (h) The timing of agency action with respect to applications subject to EISs is set forth in 40 CFR 1506.10. No decision shall be made until ninety (90) days after the Notice of Availability of the Draft Environmental Impact Statement is published in the Federal Register, and thirty (30) days after the Notice of Availability of the Final Environmental Impact Statement is published in the (i) Guidance concerning preparation of the Draft and Final Environmental Statements is set out in 40 CFR part 1502. [51 FR 15000, Apr. 22, 1986, as amended at 53 FR 28394, July 28, 1988] § 1.1315 The Draft Environmental Impact Statement (DEIS); Comments.(a) The DEIS shall include: (1) A concise description of the proposal, the nature of the area affected, its uses, and any specific feature of the area that has special environmental significance; (2) An analysis of the proposal, and reasonable alternatives exploring the important consequent advantages and/or disadvantages of the action and indicating the direct and indirect effects and their significance in terms of the short and long-term uses of the human environment. (b) When a DEIS and supplements, if any, are prepared, the Commission shall send five copies of the Statement, or a summary, to the Office of Federal Activities, Environmental Protection Agency. Additional copies, or summaries, will be sent to the appropriate regional office of the Environmental Protection Agency. Public Notice of the availability of the DEIS will be published in the (c) When copies or summaries of the DEIS are sent to the Environmental Protection Agency, the copies or summaries will be mailed with a request for comment to Federal agencies having jurisdiction by law or special expertise, to the Council on Environmental Quality, to the applicant, to individuals, groups and state and local agencies known to have an interest in the environmental consequences of a grant, and to any other person who has requested a copy. (d) Any person or agency may comment on the DEIS and the environmental effect of the proposal described therein within 45 days after notice of the availability of the statement is published in the (e) The applicant may file reply comments within 15 days after the time for filing comments has expired. Reply comments shall be filed with the Commission in the same manner as comments, and shall be served by the applicant on persons or agencies which filed comments. (f) The preparation of a DEIS and the request for comments shall not open the application to attack on other grounds. § 1.1317 The Final Environmental Impact Statement (FEIS).(a) After receipt of comments and reply comments, the Bureau will prepare a FEIS, which shall include a summary of the comments, and a response to the comments, and an analysis of the proposal in terms of its environmental consequences, and any reasonable alternatives, and recommendations, if any, and shall cite the Commission's internal appeal procedures (See 47 CFR 1.101–1.120). (b) The FEIS and any supplements will be distributed and published in the same manner as specified in §1.1315. Copies of the comments and reply comments, or summaries thereof where the record is voluminous, shall be attached to the FEIS. § 1.1319 Consideration of the environmental impact statements.(a) If the action is subject to a hearing: (1) In rendering his initial decision, the Administrative Law Judge shall utilize the FEIS in considering the environmental issues, together with all other non-environmental issues. In a comparative context, the respective parties shall be afforded the opportunity to comment on the FEIS, and the Administrative Law Judge's decision shall contain an evaluation of the respective applications based on environmental and non-environmental public interest factors. (2) Upon review of an initial decision, the Commission will consider and assess all aspects of the FEIS and will render its decision, giving due consideration to the environmental and nonenvironmental issues. (b) In all non-hearing matters, the Commission, as part of its decision-making process, will review the FEIS, along with other relevant issues, to ensure that the environmental effects are specifically assessed and given comprehensive consideration. [51 FR 15000, Apr. 22, 1986, as amended at 62 FR 4171, Jan. 29, 1997] Browse Previous | Browse Next |