Sec. 831o. Completion of unfinished plants authorized

    The board, whenever the President deems it advisable, is empowered 
and directed to complete Dam Numbered 2 at Muscle Shoals, Alabama, and 
the steam plant at nitrate plant numbered 2, in the vicinity of Muscle 
Shoals, by installing in Dam Numbered 2 the additional power units 
according to the plans and specifications of said dam, and the 
additional power unit in the steam plant at nitrate plant numbered 2.

(May 18, 1933, ch. 32, Sec. 16, 48 Stat. 67.)



chanrobles.com.Com


ChanRobles Legal Resources:

ChanRobles On-Line Bar Review

ChanRobles Internet Bar Review : www.chanroblesbar.com

ChanRobles MCLE On-line

ChanRobles Lawnet Inc. - ChanRobles MCLE On-line : www.chanroblesmcleonline.com