§ 833d. — Rate schedules; preparation, approval, and uniformity.
[Laws in effect as of January 24, 2002]
[Document not affected by Public Laws enacted between
January 24, 2002 and December 19, 2002]
[CITE: 16USC833d]
TITLE 16--CONSERVATION
CHAPTER 12C--FORT PECK PROJECT
Sec. 833d. Rate schedules; preparation, approval, and uniformity
Schedules of rates and charges for electric energy produced at the
Fort Peck project and sold to purchasers as in this chapter provided
shall be prepared by the Bureau and become effective upon confirmation
and approval thereof by the Secretary of Energy. Subject to confirmation
and approval by the Secretary of Energy, such rate schedules may be
modified from time to time by the Bureau and shall be fixed and
established with a view to encouraging the widest possible diversified
use of electric energy. The said rate schedules may provide for uniform
rate or rates uniform throughout prescribed transmission areas in order
to extend the benefits of an integrated transmission system and
encourage the equitable distribution of the electric energy developed at
the Fort Peck project.
(May 18, 1938, ch. 250, Sec. 5, 52 Stat. 405; Pub. L. 95-91, title III,
Sec. 301(b), Aug. 4, 1977, 91 Stat. 578.)
Transfer of Functions
Power marketing functions of Bureau of Reclamation, including
construction, operation, and maintenance of transmission lines and
attendant facilities, transferred to Secretary of Energy by section
7152(a)(1)(E), (3) of Title 42, The Public Health and Welfare, and are
to be exercised by Secretary through a separate Administration within
Department of Energy.
``Secretary of Energy'' substituted in text for ``Federal Power
Commission'' pursuant to Pub. L. 95-91, Sec. 301(b), which is classified
to section 7151(b) of Title 42.
Federal Power Commission terminated and its functions, personnel,
property, funds, etc., transferred to Secretary of Energy (except for
certain functions transferred to Federal Energy Regulatory Commission)
by sections 7151(b), 7171(a), 7172(a), 7291, and 7293 of Title 42.
Executive and administrative functions of Federal Power Commission,
with certain reservations, transferred to Chairman of such Commission,
with authority vested in him to authorize their performance by any
officer, employee, or administrative unit under his jurisdiction, by
Reorg. Plan No. 9 of 1950, Secs. 1, 2, eff. May 24, 1950, 15 F.R. 3175,
64 Stat. 1265, set out as a note under section 792 of this title.
For transfer of functions of other officers, employees, and agencies
of Department of the Interior, with certain exceptions, to Secretary of
the Interior, with power to delegate, see Reorg. Plan No. 3 of 1950,
Secs. 1, 2, eff. May 24, 1950, 15 F.R. 3174, 64 Stat. 1262, set out in
the Appendix to Title 5, Government Organization and Employees.