10 C.F.R. § 52.13   Relationship to subpart F of 10 CFR part 2 and appendix Q of this part.


Title 10 - Energy


Title 10: Energy
PART 52—EARLY SITE PERMITS; STANDARD DESIGN CERTIFICATIONS; AND COMBINED LICENSES FOR NUCLEAR POWER PLANTS
Subpart A—Early Site Permits

Browse Previous |  Browse Next

§ 52.13   Relationship to subpart F of 10 CFR part 2 and appendix Q of this part.

The procedures of this subpart do not replace those set out in subpart F of 10 CFR part 2 or appendix Q of this part. Subpart F applies only when early review of site suitability issues is sought in connection with an appliction for a permit to construct certain power facilities. Appendix Q applies only when NRC staff review of one or more site suitability issues is sought separately from and prior to the submittal of a construction permit. A Staff Site Report issued under appendix Q in no way affects the authority of the Commission or the presiding officer in any proceeding under subpart F or G of 10 CFR part 2. Subpart A applies when any person who may apply for a construction permit under 10 CFR part 50 or for a combined license under 10 CFR part 52 seeks an early site permit from the Commission separately from an application for a construction permit or a combined license for a facility.

Browse Previous |  Browse Next









































































chanrobles.com





ChanRobles Legal Resources:

ChanRobles On-Line Bar Review

ChanRobles Internet Bar Review : www.chanroblesbar.com

ChanRobles MCLE On-line

ChanRobles Lawnet Inc. - ChanRobles MCLE On-line : www.chanroblesmcleonline.com