10 C.F.R. § 52.24   Issuance of early site permit.


Title 10 - Energy


Title 10: Energy
PART 52—EARLY SITE PERMITS; STANDARD DESIGN CERTIFICATIONS; AND COMBINED LICENSES FOR NUCLEAR POWER PLANTS
Subpart A—Early Site Permits

Browse Previous |  Browse Next

§ 52.24   Issuance of early site permit.

After conducting a hearing under §52.21 of this subpart and receiving the report to be submitted by the Advisory Committee on Reactor Safeguards under §52.23 of this subpart, and upon determining that an application for an early site permit meets the applicable standards and requirements of the Atomic Energy Act and the Commission's regulations, and that notifications, if any, to other agencies or bodies have been duly made, the Commission shall issue an early site permit, in the form and containing the conditions and limitations, as the Commission deems appropriate and necessary.

Browse Previous |  Browse Next









































































chanrobles.com





ChanRobles Legal Resources:

ChanRobles On-Line Bar Review

ChanRobles Internet Bar Review : www.chanroblesbar.com

ChanRobles MCLE On-line

ChanRobles Lawnet Inc. - ChanRobles MCLE On-line : www.chanroblesmcleonline.com