25 C.F.R. § 1000.28   What happens if an application is not complete?


Title 25 - Indians


Title 25: Indians
PART 1000—ANNUAL FUNDING AGREEMENTS UNDER THE TRIBAL SELF-GOVERNMENT ACT AMENDMENTS TO THE INDIAN SELF-DETERMINATION AND EDUCATION ACT
Subpart B—Selection of Additional Tribes for Participation in Tribal Self-Governance
Admission Into the Applicant Pool

Browse Previous |  Browse Next

§ 1000.28   What happens if an application is not complete?

(a) If OSG determines that a Tribe's/Consortium's application is deficient, OSG will immediately notify the Tribe/Consortium of the deficiency by letter, certified mail, return receipt requested. The letter will explain what the Tribe/Consortium must do to correct the deficiency.

(b) The Tribe/Consortium will have 20 working days from the date of receiving the letter to mail or telefax the corrected material and retain the applicant's original postmark.

(c) If the corrected material is deficient, the date of entry into the applicant pool will be the date the complete application is postmarked.

(d) If the postmark or date on the applicant's response letter or telefax is more than 20 working days after the date the applicant received the notice-of-deficiency letter, the date of entry into the applicant pool will be the date of full receipt of a completed application.

Browse Previous |  Browse Next






















chanrobles.com


ChanRobles Legal Resources:

ChanRobles On-Line Bar Review

ChanRobles Internet Bar Review : www.chanroblesbar.com

ChanRobles MCLE On-line

ChanRobles Lawnet Inc. - ChanRobles MCLE On-line : www.chanroblesmcleonline.com