§ 250.197   Data and information to be made available to the public or for limited inspection.

MMS will protect data and information that you submit under this part, and part 203 of this chapter, as described in this section. Paragraphs (a) and (b) of this section describe what data and information will be made available to the public without the consent of the lessee, under what circumstances, and in what time period. Paragraph (c) of this section describes what data and information will be made available for limited inspection without the consent of the lessee, and under what circumstances.

(a) All data and information you submit on MMS forms will be made available to the public upon submission, except as specified in the following table:

 ------------------------------------------------------------------------                                     Data and                                 information not         On form . . .             immediately     Excepted data will be                                available are . .   made available . . .                                        .------------------------------------------------------------------------(1) MMS-123, Application for    Items 15, 16, 22   When the well goes on Permit to Drill.                through 25.        production or                                                    according to the                                                    table in paragraph                                                    (b) of this section,                                                    whichever is                                                    earlier.(2) MMS-123S, Supplemental APD  Items 3, 7, 8, 15  When the well goes on Information Sheet.              and 17.            production or                                                    according to the                                                    table in paragraph                                                    (b) of this section,                                                    whichever is                                                    earlier.(3) MMS-124, Application for    Item 17..........  When the well goes on Permit to Modify.                                  production or                                                    according to the                                                    table in paragraph                                                    (b) of this section,                                                    whichever is                                                    earlier.(4) MMS-125, End of Operations  Items 12, 13, 17,  When the well goes on Report.                         21, 22, 26         production or                                 through 38.        according to the                                                    table in paragraph                                                    (b) of this section,                                                    whichever is                                                    earlier. However,                                                    items 33 through 38                                                    will not be released                                                    when the well goes                                                    on production unless                                                    the period of time                                                    in the table in                                                    paragraph (b) has                                                    expired.(5) MMS-126, Well Potential     Item 101.........  2 years after you Test Report.                                       submit it.(6) MMS-127, Sensitive          Items 124 through  2 years after the Reservoir Information Report.   168.               effective date of                                                    the Sensitive                                                    Reservoir                                                    Information Report.(7) MMS-133 Well Activity       Item 10 Fields     When the well goes on Report.                         [WELLBORE START    production or                                 DATE, TD DATE,     according to the                                 OP STATUS, END     table in paragraph                                 DATE, MD, TVD,     (b) of this section,                                 AND MW PPG].       whichever is                                 Item 11 Fields     earlier.                                 [WELLBORE START                                 DATE, TD DATE,                                 PLUGBACK DATE,                                 FINAL MD, AND                                 FINAL TVD] and                                 Items 12 through                                 15.(8) MMS-133S Open Hole Data     Boxes 7 and 8....  When the well goes on Report.                                            production or                                                    according to the                                                    table in paragraph                                                    (b) of this seciton,                                                    whichever is                                                    earlier.(9) MMS-137 OCS Plan            Items providing    When the well goes on Information.                    the bottomhole     production or                                 location, true     according to the                                 vertical depth,    table in paragraph                                 and measured       (b) of this section,                                 depth of wells.    whichever is                                                    earlier.(10) MMS-140, Bottomhole        All items........  2 years after the Pressure Survey Report.                            date of the survey.------------------------------------------------------------------------

(b) MMS will release lease and permit data and information that you submit and MMS retains, but that are not normally submitted on MMS forms, according to the following table:

 ----------------------------------------------------------------------------------------------------------------                 If                     MMS will release          At this time            Special provisions----------------------------------------------------------------------------------------------------------------(1) The Director determines that     Geophysical data,       At any time...........  MMS will release data and data and information are needed      Geological data                                 information only if for specific scientific or           Interpreted G&G                             release would further the research purposes for the            information,                                    national interest without Government.                          Processed G&G                               unduly damaging the                                      information, Analyzed                           competitive position of                                      geological                                      the lessee.                                      information.(2) Data or information is           Geophysical data,       60 days after MMS       MMS will release the data collected with high-resolution       Geological data,        receives the data or    and information earlier systems (e.g., bathymetry, side-     Interpreted G&G     information, if the     than 60 days if the scan sonar, subbottom profiler,      information,            Regional Supervisor     Regional Supervisor and magnetometer) to comply with     Processed geological    deems it necessary.     determines it is needed by safety or environmental protection   information, Analyzed                           affected States to make requirements.                        geological                                      decisions under subpart B.                                      information.                                    The Regional Supervisor                                                                                      will reconsider earlier                                                                                      release if you satisfy him/                                                                                      her that it would unduly                                                                                      damage your competitive                                                                                      position.(3) Your lease is no longer in       Geophysical data,       When your lease         This release time applies effect.                              Geological data,        terminates.             only if the provisions in                                      Processed G&G                               this table governing high-                                      information                                     resolution systems and the                                      Interpreted G&G                             provisions in § 252.7                                      information, Analyzed                           do not apply. The release                                      geological                                      time applies to the                                      information.                                    geophysical data and                                                                                      information only if                                                                                      acquired postlease for a                                                                                      lessee's exclusive use.(4) Your lease is still in effect..  Geophysical data        10 years after you      This release time applies                                      Processed geophysical   submit the data and     only if the provisions in                                      information,            information.            this table governing high-                                      Interpreted G&G                             resolution systems and the                                      information.                                    provisions in § 252.7                                                                                      do not apply. This release                                                                                      time applies to the                                                                                      geophysical data and                                                                                      information only if                                                                                      acquired postlease for a                                                                                      lessee's exclusive use.(5) Your lease is still in effect    Geological data,        2 years after the       These release times apply and within the primary term          Analyzed geological     required submittal      only if the provisions in specified in the lease.              information.            date or 60 days after   this table governing high-                                                              a lease sale if any     resolution systems and the                                                              portion of an offered   provisions in § 252.7                                                              lease is within 50      do not apply. If the                                                              miles of a well,        primary term specified in                                                              whichever is later.     the lease is extended                                                                                      under the heading of                                                                                      ``Suspensions'' in this                                                                                      subpart, the extension                                                                                      applies to this provision.(6) Your lease is in effect and      Geological data,        2 years after the       None. beyond the primary term specified    Analyzed geological     required submittal in the lease.                        information.            date.(7) Data or information is           Descriptions of         When the well goes on   Directional survey data may submitted on well operations.        downhole locations,     production or when      be released earlier to the                                      operations, and         geological data is      owner of an adjacent lease                                      equipment.              released according to   according to Subpart D of                                                              §§            this part.                                                              250.197(b)(6) and                                                              (b)(7), whichever                                                              occurs earlier.(8) Data and information are         Any data or             At any time...........  None. obtained from beneath unleased       information obtained. land as a result of a well deviation that has not been approved by the District Manager or Regional Supervisor.(9) Except for high-resolution data  G&G data, analyzed  Geological data and     None. and information released under       geological              information: 10 years paragraph (b)(2) of this section     information,            after MMS issues the data and information acquired by a   processed and           permit; Geophysical permit under part 251 are            interpreted G&G     data: 50 years after submitted by a lessee under 30 CFR   information.            MMS issues the part 203 or part 250.                                        permit; Geophysical                                                              information: 25 years                                                              after MMS issues the                                                              permit.----------------------------------------------------------------------------------------------------------------

(c) MMS may allow limited inspection, but only by persons with a direct interest in related MMS decisions and issues in specific geographic areas, and who agree in writing to its confidentiality, of G&G data and information submitted under this part or part 203 of this chapter that MMS uses to:

(1) Make unitization determinations on two or more leases;

(2) Make competitive reservoir determinations;

(3) Ensure proper plans of development for competitive reservoirs;

(4) Promote operational safety;

(5) Protect the environment;

(6) Make field determinations; or

(7) Determine eligibility for royalty relief.