30 C.F.R. PART 250--OIL AND GAS AND SULPHUR OPERATIONS IN THE OUTER CONTINENTAL SHELF


TITLE 30--Mineral Resources

CHAPTER II--MINERALS MANAGEMENT SERVICE, DEPARTMENT OF THE INTERIOR

SUBCHAPTER B--OFFSHORE

PART 250--OIL AND GAS AND SULPHUR OPERATIONS IN THE OUTER CONTINENTAL SHELF

rule

Subpart A--GENERAL

�250.101
Authority and applicability.
�250.102
What does this part do?
�250.103
Where can I find more information about the requirements in this part?
�250.104
How may I appeal a decision made under MMS regulations?
�250.105
Definitions.
�250.106
What standards will the Director use to regulate lease operations?
�250.107
What must I do to protect health, safety, property, and the environment?
�250.108
What requirements must I follow for cranes and other material-handling equipment?
�250.109
What documents must I prepare and maintain related to welding?
�250.110
What must I include in my welding plan?
�250.111
Who oversees operations under my welding plan?
�250.112
What standards must my welding equipment meet?
�250.113
What procedures must I follow when welding?
�250.114
How must I install and operate electrical equipment?
�250.115
How do I determine well producibility?
�250.116
How do I determine producibility if my well is in the Gulf of Mexico?
�250.117
How does a determination of well producibility affect royalty status?
�250.118
Will MMS approve gas injection?
�250.119
Will MMS approve subsurface gas storage?
�250.120
How does injecting, storing, or treating gas affect my royalty payments?
�250.121
What happens when the reservoir contains both original gas in place and injected gas?
�250.122
What effect does subsurface storage have on the lease term?
�250.123
Will MMS allow gas storage on unleased lands?
�250.124
Will MMS approve gas injection into the cap rock containing a sulphur deposit?
�250.125
Service fees.
�250.126
xxx
�250.130
Why does MMS conduct inspections?
�250.131
Will MMS notify me before conducting an inspection?
�250.132
What must I do when MMS conducts an inspection?
�250.133
Will MMS reimburse me for my expenses related to inspections?
�250.135
What will MMS do if my operating performance is unacceptable?
�250.136
How will MMS determine if my operating performance is unacceptable?
�250.140
When will I receive an oral approval?
�250.141
May I ever use alternate procedures or equipment?
�250.142
How do I receive approval for departures?
�250.143
How do I designate an operator?
�250.144
How do I designate a new operator when a designation of operator terminates?
�250.145
How do I designate an agent or a local agent?
�250.146
Who is responsible for fulfilling leasehold obligations?
�250.150
How do I name facilities and wells in the Gulf of Mexico Region?
�250.151
How do I name facilities in the Pacific Region?
�250.152
How do I name facilities in the Alaska Region?
�250.153
Do I have to rename an existing facility or well?
�250.154
What identification signs must I display?
�250.160
When will MMS grant me a right-of-use and easement, and what requirements must I meet?
�250.161
What else must I submit with my application?
�250.162
May I continue my right-of-use and easement after the termination of any lease on which it is situated?
�250.163
If I have a State lease, will MMS grant me a right-of-use and easement?
�250.164
If I have a State lease, what conditions apply for a right-of-use and easement?
�250.165
If I have a State lease, what fees do I have to pay for a right-of-use and easement?
�250.166
If I have a State lease, what surety bond must I have for a right-of-use and easement?
�250.168
May operations or production be suspended?
�250.169
What effect does suspension have on my lease?
�250.170
How long does a suspension last?
�250.171
How do I request a suspension?
�250.172
When may the Regional Supervisor grant or direct an SOO or SOP?
�250.173
When may the Regional Supervisor direct an SOO or SOP?
�250.174
When may the Regional Supervisor grant or direct an SOP?
�250.175
When may the Regional Supervisor grant an SOO?
�250.176
Does a suspension affect my royalty payment?
�250.177
What additional requirements may the Regional Supervisor order for a suspension?
�250.180
What am I required to do to keep my lease term in effect?
�250.181
When may the Secretary cancel my lease and when am I compensated for cancellation?
�250.182
When may the Secretary cancel a lease at the exploration stage?
�250.183
When may MMS or the Secretary extend or cancel a lease at the development and production stage?
�250.184
What is the amount of compensation for lease cancellation?
�250.185
When is there no compensation for a lease cancellation?
�250.186
What reporting information and report forms must I submit?
�250.187
What are MMS' incident reporting requirements?
�250.188
What incidents must I report to MMS and when must I report them?
�250.189
Reporting requirements for incidents requiring immediate notification.
�250.190
Reporting requirements for incidents requiring written notification.
�250.191
How does MMS conduct incident investigations?
�250.192
What evacuation statistics must I submit?
�250.193
Reports and investigations of apparent violations.
�250.194
How must I protect archaeological resources?
�250.195
What notification does MMS require on the production status of wells?
�250.196
Reimbursements for reproduction and processing costs.
�250.197
Data and information to be made available to the public or for limited inspection.
�250.198
Documents incorporated by reference.
�250.199
Paperwork Reduction Act statements--information collection.
rule

Subpart B--PLANS AND INFORMATION

�250.200
Definitions.
�250.201
What plans and information must I submit before I conduct any activities on my lease or unit?
�250.202
What criteria must the Exploration Plan (EP), Development and Production Plan (DPP), or Development Operations Coordination Document (DOCD) meet?
�250.203
Where can wells be located under an EP, DPP, or DOCD?
�250.204
How must I protect the rights of the Federal government?
�250.205
Are there special requirements if my well affects an adjacent property?
�250.206
How do I submit the EP, DPP, or DOCD?
�250.207
What ancillary activities may I conduct?
�250.208
If I conduct ancillary activities, what notices must I provide?
�250.209
What is the MMS review process for the notice?
�250.210
If I conduct ancillary activities, what reporting and data/information retention requirements must I satisfy?
�250.211
What must the EP include?
�250.212
What information must accompany the EP?
�250.213
What general information must accompany the EP?
�250.214
What geological and geophysical (G&G) information must accompany the EP?
�250.215
What hydrogen sulfide (H2S) information must accompany the EP?
�250.216
What biological, physical, and socioeconomic information must accompany the EP?
�250.217
What solid and liquid wastes and discharges information and cooling water intake information must accompany the EP?
�250.218
What air emissions information must accompany the EP?
�250.219
What oil and hazardous substance spills information must accompany the EP?
�250.220
If I propose activities in the Alaska OCS Region, what planning information must accompany the EP?
�250.221
What environmental monitoring information must accompany the EP?
�250.222
What lease stipulations information must accompany the EP?
�250.223
What mitigation measures information must accompany the EP?
�250.224
What information on support vessels, offshore vehicles, and aircraft you will use must accompany the EP?
�250.225
What information on the onshore support facilities you will use must accompany the EP?
�250.226
What Coastal Zone Management Act (CZMA) information must accompany the EP?
�250.227
What environmental impact analysis (EIA) information must accompany the EP?
�250.228
What administrative information must accompany the EP?
�250.231
After receiving the EP, what will MMS do?
�250.232
What actions will MMS take after the EP is deemed submitted?
�250.233
What decisions will MMS make on the EP and within what timeframe?
�250.234
How do I submit a modified EP or resubmit a disapproved EP, and when will MMS make a decision?
�250.235
If a State objects to the EP's coastal zone consistency certification, what can I do?
�250.241
What must the DPP or DOCD include?
�250.242
What information must accompany the DPP or DOCD?
�250.243
What general information must accompany the DPP or DOCD?
�250.244
What geological and geophysical (G&G) information must accompany the DPP or DOCD?
�250.245
What hydrogen sulfide (H2S) information must accompany the DPP or DOCD?
�250.246
What mineral resource conservation information must accompany the DPP or DOCD?
�250.247
What biological, physical, and socioeconomic information must accompany the DPP or DOCD?
�250.248
What solid and liquid wastes and discharges information and cooling water intake information must accompany the DPP or DOCD?
�250.249
What air emissions information must accompany the DPP or DOCD?
�250.250
What oil and hazardous substance spills information must accompany the DPP or DOCD?
�250.251
If I propose activities in the Alaska OCS Region, what planning information must accompany the DPP?
�250.252
What environmental monitoring information must accompany the DPP or DOCD?
�250.253
What lease stipulations information must accompany the DPP or DOCD?
�250.254
What mitigation measures information must accompany the DPP or DOCD?
�250.255
What decommissioning information must accompany the DPP or DOCD?
�250.256
What related facilities and operations information must accompany the DPP or DOCD?
�250.257
What information on the support vessels, offshore vehicles, and aircraft you will use must accompany the DPP or DOCD?
�250.258
What information on the onshore support facilities you will use must accompany the DPP or DOCD?
�250.259
What sulphur operations information must accompany the DPP or DOCD?
�250.260
What Coastal Zone Management Act (CZMA) information must accompany the DPP or DOCD?
�250.261
What environmental impact analysis (EIA) information must accompany the DPP or DOCD?
�250.262
What administrative information must accompany the DPP or DOCD?
�250.266
After receiving the DPP or DOCD, what will MMS do?
�250.267
What actions will MMS take after the DPP or DOCD is deemed submitted?
�250.268
How does MMS respond to recommendations?
�250.269
How will MMS evaluate the environmental impacts of the DPP or DOCD?
�250.270
What decisions will MMS make on the DPP or DOCD and within what timeframe?
�250.271
For what reasons will MMS disapprove the DPP or DOCD?
�250.272
If a State objects to the DPP's or DOCD's coastal zone consistency certification, what can I do?
�250.273
How do I submit a modified DPP or DOCD or resubmit a disapproved DPP or DOCD?
�250.280
How must I conduct activities under the approved EP, DPP, or DOCD?
�250.281
What must I do to conduct activities under the approved EP, DPP, or DOCD?
�250.282
Do I have to conduct post-approval monitoring?
�250.283
When must I revise or supplement the approved EP, DPP, or DOCD?
�250.284
How will MMS require revisions to the approved EP, DPP, or DOCD?
�250.285
How do I submit revised and supplemental EPs, DPPs, and DOCDs?
�250.286
What is a DWOP?
�250.287
For what development projects must I submit a DWOP?
�250.288
When and how must I submit the Conceptual Plan?
�250.289
What must the Conceptual Plan contain?
�250.290
What operations require approval of the Conceptual Plan?
�250.291
When and how must I submit the DWOP?
�250.292
What must the DWOP contain?
�250.293
What operations require approval of the DWOP?
�250.294
May I combine the Conceptual Plan and the DWOP?
�250.295
When must I revise my DWOP?
�250.296
When and how must I submit a CID or a revision to a CID?
�250.297
What information must a CID contain?
�250.298
How long will MMS take to evaluate and make a decision on the CID?
�250.299
What operations require approval of the CID?
rule

Subpart C--POLLUTION PREVENTION AND CONTROL

�250.300
Pollution prevention.
�250.301
Inspection of facilities.
�250.302
Definitions concerning air quality.
�250.303
Facilities described in a new or revised Exploration Plan or Development and Production Plan.
�250.304
Existing facilities.
rule

Subpart D--OIL AND GAS DRILLING OPERATIONS

�250.400
Who is subject to the requirements of this subpart?
�250.401
What must I do to keep wells under control?
�250.402
When and how must I secure a well?
�250.403
What drilling unit movements must I report?
�250.404
What are the requirements for the crown block?
�250.405
What are the safety requirements for diesel engines used on a drilling rig?
�250.406
What additional safety measures must I take when I conduct drilling operations on a platform that has producing wells or has other hydrocarbon flow?
�250.407
What tests must I conduct to determine reservoir characteristics?
�250.408
May I use alternative procedures or equipment during drilling operations?
�250.409
May I obtain departures from these drilling requirements?
�250.410
How do I obtain approval to drill a well?
�250.411
What information must I submit with my application?
�250.412
What requirements must the location plat meet?
�250.413
What must my description of well drilling design criteria address?
�250.414
What must my drilling prognosis include?
�250.415
What must my casing and cementing programs include?
�250.416
What must I include in the diverter and BOP descriptions?
�250.417
What must I provide if I plan to use a mobile offshore drilling unit (MODU)?
�250.418
What additional information must I submit with my APD?
�250.420
What well casing and cementing requirements must I meet?
�250.421
What are the casing and cementing requirements by type of casing string?
�250.422
When may I resume drilling after cementing?
�250.423
What are the requirements for pressure testing casing?
�250.424
What are the requirements for prolonged drilling operations?
�250.425
What are the requirements for pressure testing liners?
�250.426
What are the recordkeeping requirements for casing and liner pressure tests?
�250.427
What are the requirements for pressure integrity tests?
�250.428
What must I do in certain cementing and casing situations?
�250.430
When must I install a diverter system?
�250.431
What are the diverter design and installation requirements?
�250.432
How do I obtain a departure to diverter design and installation requirements?
�250.433
What are the diverter actuation and testing requirements?
�250.434
What are the recordkeeping requirements for diverter actuations and tests?
�250.440
What are the general requirements for BOP systems and system components?
�250.441
What are the requirements for a surface BOP stack?
�250.442
What are the requirements for a subsea BOP stack?
�250.443
What associated systems and related equipment must all BOP systems include?
�250.444
What are the choke manifold requirements?
�250.445
What are the requirements for kelly valves, inside BOPs, and drill-string safety valves?
�250.446
What are the BOP maintenance and inspection requirements?
�250.447
When must I pressure test the BOP system?
�250.448
What are the BOP pressure tests requirements?
�250.449
What additional BOP testing requirements must I meet?
�250.450
What are the recordkeeping requirements for BOP tests?
�250.451
What must I do in certain situations involving BOP equipment or systems?
�250.455
What are the general requirements for a drilling fluid program?
�250.456
What safe practices must the drilling fluid program follow?
�250.457
What equipment is required to monitor drilling fluids?
�250.458
What quantities of drilling fluids are required?
�250.459
What are the safety requirements for drilling fluid-handling areas?
�250.460
What are the requirements for conducting a well test?
�250.461
What are the requirements for directional and inclination surveys?
�250.462
What are the requirements for well-control drills?
�250.463
Who establishes field drilling rules?
�250.465
When must I submit an Application for Permit to Modify (APM) or an End of Operations Report to MMS?
�250.466
What records must I keep?
�250.467
How long must I keep records?
�250.468
What well records am I required to submit?
�250.469
What other well records could I be required to submit?
�250.490
Hydrogen sulfide.
rule

Subpart E--OIL AND GAS WELL-COMPLETION OPERATIONS

�250.500
General requirements.
�250.501
Definition.
�250.502
Equipment movement.
�250.503
Emergency shutdown system.
�250.504
Hydrogen sulfide.
�250.505
Subsea completions.
�250.506
Crew instructions.
��250.507-250.508
[Reserved]
�250.509
Well-completion structures on fixed platforms.
�250.510
Diesel engine air intakes.
�250.511
Traveling-block safety device.
�250.512
Field well-completion rules.
�250.513
Approval and reporting of well-completion operations.
�250.514
Well-control fluids, equipment, and operations.
�250.515
Blowout prevention equipment.
�250.516
Blowout preventer system tests, inspections, and maintenance.
�250.517
Tubing and wellhead equipment.
rule

Subpart F--OIL AND GAS WELL-WORKOVER OPERATIONS

�250.600
General requirements.
�250.601
Definitions.
�250.602
Equipment movement.
�250.603
Emergency shutdown system.
�250.604
Hydrogen sulfide.
�250.605
Subsea workovers.
�250.606
Crew instructions.
��250.607-250.608
[Reserved]
�250.609
Well-workover structures on fixed platforms.
�250.610
Diesel engine air intakes.
�250.611
Traveling-block safety device.
�250.612
Field well-workover rules.
�250.613
Approval and reporting for well-workover operations.
�250.614
Well-control fluids, equipment, and operations.
�250.615
Blowout prevention equipment.
�250.616
Blowout preventer system testing, records, and drills.
�250.617
Tubing and wellhead equipment.
�250.618
Wireline operations.
rule

Subpart G--[RESERVED]

rule

Subpart H--OIL AND GAS PRODUCTION SAFETY SYSTEMS

�250.800
General requirements.
�250.801
Subsurface safety devices.
�250.802
Design, installation, and operation of surface production-safety systems.
�250.803
Additional production system requirements.
�250.804
Production safety-system testing and records.
�250.805
Safety device training.
�250.806
Safety and pollution prevention equipment quality assurance requirements.
�250.807
Hydrogen sulfide.
rule

Subpart I--PLATFORMS AND STRUCTURES

�250.900
What general requirements apply to all platforms?
�250.901
What industry standards must your platform meet?
�250.902
What are the requirements for platform removal and location clearance?
�250.903
What records must I keep?
�250.904
What is the Platform Approval Program?
�250.905
How do I get approval for the installation, modification, or repair of my platform?
�250.906
What must I do to obtain approval for the proposed site of my platform?
�250.907
Where must I locate foundation boreholes?
�250.908
What are the minimum structural fatigue design requirements?
�250.909
What is the Platform Verification Program?
�250.910
Which of my facilities are subject to the Platform Verification Program?
�250.911
If my platform is subject to the Platform Verification Program, what must I do?
�250.912
What plans must I submit under the Platform Verification Program?
�250.913
When must I resubmit Platform Verification Program plans?
�250.914
How do I nominate a CVA?
�250.915
What are the CVA's primary responsibilities?
�250.916
What are the CVA's primary duties during the design phase?
�250.917
What are the CVA's primary duties during the fabrication phase?
�250.918
What are the CVA's primary duties during the installation phase?
�250.919
What in-service inspection requirements must I meet?
�250.920
What are the MMS requirements for assessment of platforms?
�250.921
How do I analyze my platform for cumulative fatigue?
rule

Subpart J--PIPELINES AND PIPELINE RIGHTS-OF-WAY

�250.1000
General requirements.
�250.1001
Definitions.
�250.1002
Design requirements for DOI pipelines.
�250.1003
Installation, testing, and repair requirements for DOI pipelines.
�250.1004
Safety equipment requirements for DOI pipelines.
�250.1005
Inspection requirements for DOI pipelines.
�250.1006
How must I decommission and take out of service a DOI pipeline?
�250.1007
What to include in applications.
�250.1008
Reports.
�250.1009
Requirements to obtain pipeline right-of-way grants.
�250.1010
General requirements for pipeline right-of-way holders.
�250.1011
Bond requirements for pipeline right-of-way holders.
�250.1012
Required payments for pipeline right-of-way holders.
�250.1013
Grounds for forfeiture of pipeline right-of-way grants.
�250.1014
When pipeline right-of-way grants expire.
�250.1015
Applications for pipeline right-of-way grants.
�250.1016
Granting pipeline rights-of-way.
�250.1017
Requirements for construction under pipeline right-of-way grants.
�250.1018
Assignment of pipeline right-of-way grants.
�250.1019
Relinquishment of pipeline right-of-way grants.
rule

Subpart K--OIL AND GAS PRODUCTION RATES

�250.1100
Definitions for production rates.
�250.1101
General requirements and classification of reservoirs.
�250.1102
Oil and gas production rates.
�250.1103
Well production testing.
�250.1104
Bottomhole pressure survey.
�250.1105
Flaring or venting gas and burning liquid hydrocarbons.
�250.1106
Downhole commingling.
�250.1107
Enhanced oil and gas recovery operations.
rule

Subpart L--OIL AND GAS PRODUCTION MEASUREMENT, SURFACE COMMINGLING, AND SECURITY

�250.1200
Question index table.
�250.1201
Definitions.
�250.1202
Liquid hydrocarbon measurement.
�250.1203
Gas measurement.
�250.1204
Surface commingling.
�250.1205
Site security.
rule

Subpart M--UNITIZATION

�250.1300
What is the purpose of this subpart?
�250.1301
What are the requirements for unitization?
�250.1302
What if I have a competitive reservoir on a lease?
�250.1303
How do I apply for voluntary unitization?
�250.1304
How will MMS require unitization?
rule

Subpart N--OUTER CONTINENTAL SHELF (OCS) CIVIL PENALTIES

�250.1400
How does MMS begin the civil penalty process?
�250.1401
Index table.
�250.1402
Definitions.
�250.1403
What is the maximum civil penalty?
�250.1404
Which violations will MMS review for potential civil penalties?
�250.1405
When is a case file developed?
�250.1406
When will MMS notify me and provide penalty information?
�250.1407
How do I respond to the letter of notification?
�250.1408
When will I be notified of the Reviewing Officer's decision?
�250.1409
What are my appeal rights?
rule

Subpart O--WELL CONTROL AND PRODUCTION SAFETY TRAINING

�250.1500
Definitions.
�250.1501
What is the goal of my training program?
�250.1502
Is there a transition period for complying with the regulations in this subpart?
�250.1503
What are my general responsibilities for training?
�250.1504
May I use alternative training methods?
�250.1505
Where may I get training for my employees?
�250.1506
How often must I train my employees?
�250.1507
How will MMS measure training results?
�250.1508
What must I do when MMS administers written or oral tests?
�250.1509
What must I do when MMS administers or requires hands-on, simulator, or other types of testing?
�250.1510
What will MMS do if my training program does not comply with this subpart?
rule

Subpart P--SULPHUR OPERATIONS

�250.1600
Performance standard.
�250.1601
Definitions.
�250.1602
Applicability.
�250.1603
Determination of sulphur deposit.
�250.1604
General requirements.
�250.1605
Drilling requirements.
�250.1606
Control of wells.
�250.1607
Field rules.
�250.1608
Well casing and cementing.
�250.1609
Pressure testing of casing.
�250.1610
Blowout preventer systems and system components.
�250.1611
Blowout preventer systems tests, actuations, inspections, and maintenance.
�250.1612
Well-control drills.
�250.1613
Diverter systems.
�250.1614
Mud program.
�250.1615
Securing of wells.
�250.1616
Supervision, surveillance, and training.
�250.1617
Application for permit to drill.
�250.1618
Sundry notices and reports on wells.
�250.1619
Well records.
�250.1620
Well-completion and well-workover requirements.
�250.1621
Crew instructions.
�250.1622
Approvals and reporting of well-completion and well-workover operations.
�250.1623
Well-control fluids, equipment, and operations.
�250.1624
Blowout prevention equipment.
�250.1625
Blowout preventer system testing, records, and drills.
�250.1626
Tubing and wellhead equipment.
�250.1627
Production requirements.
�250.1628
Design, installation, and operation of production systems.
�250.1629
Additional production and fuel gas system requirements.
�250.1630
Safety-system testing and records.
�250.1631
Safety device training.
�250.1632
Production rates.
�250.1633
Production measurement.
�250.1634
Site security.
rule

Subpart Q--DECOMMISSIONING ACTIVITIES

�250.1700
What do the terms ''decommissioning'', ''obstructions'', and ''facility'' mean?
�250.1701
Who must meet the decommissioning obligations in this subpart?
�250.1702
When do I accrue decommissioning obligations?
�250.1703
What are the general requirements for decommissioning?
�250.1704
When must I submit decommissioning applications and reports?
�250.1710
When must I permanently plug all wells on a lease?
�250.1711
When will MMS order me to permanently plug a well?
�250.1712
What information must I submit before I permanently plug a well or zone?
�250.1713
Must I notify MMS before I begin well plugging operations?
�250.1714
What must I accomplish with well plugs?
�250.1715
How must I permanently plug a well?
�250.1716
To what depth must I remove wellheads and casings?
�250.1717
After I permanently plug a well, what information must I submit?
�250.1721
If I temporarily abandon a well that I plan to re-enter, what must I do?
�250.1722
If I install a subsea protective device, what requirements must I meet?
�250.1723
What must I do when it is no longer necessary to maintain a well in temporary abandoned status?
�250.1725
When do I have to remove platforms and other facilities?
�250.1726
When must I submit an initial platform removal application and what must it include?
�250.1727
What information must I include in my final application to remove a platform or other facility?
�250.1728
To what depth must I remove a platform or other facility?
�250.1729
After I remove a platform or other facility, what information must I submit?
�250.1730
When might MMS approve partial structure removal or toppling in place?
�250.1740
How must I verify that the site of a permanently plugged well, removed platform, or other removed facility is clear of obstructions?
�250.1741
If I drag a trawl across a site, what requirements must I meet?
�250.1742
What other methods can I use to verify that a site is clear?
�250.1743
How do I certify that a site is clear of obstructions?
�250.1750
When may I decommission a pipeline in place?
�250.1751
How do I decommission a pipeline in place?
�250.1752
How do I remove a pipeline?
�250.1753
After I decommission a pipeline, what information must I submit?
�250.1754
When must I remove a pipeline decommissioned in place?
rule























chanrobles.com


ChanRobles Legal Resources:

ChanRobles On-Line Bar Review

ChanRobles Internet Bar Review : www.chanroblesbar.com

ChanRobles MCLE On-line

ChanRobles Lawnet Inc. - ChanRobles MCLE On-line : www.chanroblesmcleonline.com