§ 250.449   What additional BOP testing requirements must I meet?

You must meet the following additional BOP testing requirements:

(a) Use water to test a surface BOP system;

(b) Stump test a subsea BOP system before installation. You must use water to conduct this test. You may use drilling fluids to conduct subsequent tests of a subsea BOP system;

(c) Alternate tests between control stations and pods;

(d) Pressure test the blind or blind-shear ram BOP during stump tests and at all casing points;

(e) The interval between any blind or blind-shear ram BOP pressure tests may not exceed 30 days;

(f) Pressure test variable bore-pipe ram BOPs against the largest and smallest sizes of pipe in use, excluding drill collars and bottom-hole tools;

(g) Pressure test affected BOP components following the disconnection or repair of any well-pressure containment seal in the wellhead or BOP stack assembly;

(h) Function test annular and ram BOPs every 7 days between pressure tests; and

(i) Actuate safety valves assembled with proper casing connections before running casing.

[68 FR 8423, Feb. 20, 2003]

Browse Previous |  Browse Next






















chanrobles.com


ChanRobles Legal Resources:

ChanRobles On-Line Bar Review

ChanRobles Internet Bar Review : www.chanroblesbar.com

ChanRobles MCLE On-line

ChanRobles Lawnet Inc. - ChanRobles MCLE On-line : www.chanroblesmcleonline.com