30 C.F.R. § 250.209 What is the MMS review process for the notice?
Title 30 - Mineral Resources
The Regional Supervisor will review any notice required under §250.208(a) and (b)(1) to ensure that your ancillary activity complies with the performance standards listed in §250.202(a), (b), (d), and (e). The Regional Supervisor may notify you that your ancillary activity does not comply with those standards. In such a case, the Regional Supervisor will require you to submit an EP, DPP, or DOCD and you may not start your ancillary activity until the Regional Supervisor approves the EP, DPP, or DOCD.
Title 30: Mineral Resources
PART 250—OIL AND GAS AND SULPHUR OPERATIONS IN THE OUTER CONTINENTAL SHELF
Subpart B—Plans and Information
Ancillary Activities
§ 250.209 What is the MMS review process for the notice?