30 C.F.R. § 250.1717 After I permanently plug a well, what information must I submit?
Title 30 - Mineral Resources
Within 30 days after you permanently plug a well, you must submit form MMS–124, Application for Permit to Modify (subsequent report), to the appropriate District Manager, and include the following information: (a) Information included in §250.1712 with a final well schematic; (b) Description of the plugging work; (c) Nature and quantities of material used in the plugs; and (d) If you cut and pulled any casing string, the following information: (1) A description of the methods used (including information on explosives, if used); (2) Size and amount of casing removed; and (3) Casing removal depth. [67 FR 35406, May 17, 2002; 67 FR 66049, Oct. 30, 2002]
Title 30: Mineral Resources
PART 250—OIL AND GAS AND SULPHUR OPERATIONS IN THE OUTER CONTINENTAL SHELF
Subpart Q—Decommissioning Activities
Permanently Plugging Wells
§ 250.1717 After I permanently plug a well, what information must I submit?