30 C.F.R. § 250.1012   Required payments for pipeline right-of-way holders.


Title 30 - Mineral Resources


Title 30: Mineral Resources
PART 250—OIL AND GAS AND SULPHUR OPERATIONS IN THE OUTER CONTINENTAL SHELF
Subpart J—Pipelines and Pipeline Rights-of-Way

Browse Previous |  Browse Next

§ 250.1012   Required payments for pipeline right-of-way holders.

(a) You must pay MMS an annual rental of $15 for each statute mile, or part of a statute mile, of the OCS that your pipeline right-of-way crosses.

(b) This paragraph applies to you if you obtain a pipeline right-of-way that includes a site for an accessory to the pipeline, including but not limited to a platform. This paragraph also applies if you apply to modify a right-of-way to change the site footprint. In either case, you must pay the amounts shown in the following table.

 ------------------------------------------------------------------------               If...                               Then...------------------------------------------------------------------------(1) Your accessory site is located   You must pay a rental of $5 per in water depths of less than 200     acre per year with a minimum of meters;                              $450 per year. The area subject to                                      annual rental includes the areal                                      extent of anchor chains, pipeline                                      risers, and other facilities and                                      devices associated with the                                      accessory.(2) Your accessory site is located   You must pay a rental of $7.50 per in water depths of 200 meters or     acre per year with a minimum of greater;                             $675 per year. The area subject to                                      annual rental includes the areal                                      extent of anchor chains, pipeline                                      risers, and other facilities and                                      devices associated with the                                      accessory.------------------------------------------------------------------------

(c) If you hold a pipeline right-of-way that includes a site for an accessory to your pipeline and you are not covered by paragraph (b) of this section, then you must pay MMS an annual rental of $75 for use of the affected area.

(d) You may make the rental payments required by paragraphs (a), (b)(1), (b)(2), and (c) of this section on an annual basis, for a 5-year period, or for multiples of 5 years. You must make the first payment at the time you submit the pipeline right-of-way application. You must make all subsequent payments before the respective time periods begin.

(e) Late payments. An interest charge will be assessed on unpaid and underpaid amounts from the date the amounts are due, in accordance with the provisions found in 30 CFR 218.54. If you fail to make a payment that is late after written notice from MMS, MMS may initiate cancellation of the right-of-use grant and easement under 30 CFR 250.1013.

[68 FR 69312, Dec. 12, 2003, as amended at 69 FR 29433, May 24, 2004]