30 C.F.R. § 250.913 When must I resubmit Platform Verification Program plans?
Title 30 - Mineral Resources
(a) You must resubmit any design verification, fabrication verification, or installation verification plan to the Regional Supervisor for approval if: (1) The CVA changes; (2) The CVA's or assigned personnel's qualifications change; or (3) The level of work to be performed changes. (b) If only part of a verification plan is affected by one of the changes described in paragraph (a) of this section, you can resubmit only the affected part. You do not have to resubmit the summary of technical details unless you make changes in the technical details.
Title 30: Mineral Resources
PART 250—OIL AND GAS AND SULPHUR OPERATIONS IN THE OUTER CONTINENTAL SHELF
Subpart I—Platforms and Structures
Platform Verification Program
§ 250.913 When must I resubmit Platform Verification Program plans?