32 C.F.R. Subpart G—Award Terms Related to Other Administrative Matters


Title 32 - National Defense


Title 32: National Defense
PART 37—TECHNOLOGY INVESTMENT AGREEMENTS

Browse Previous |  Browse Next

Subpart G—Award Terms Related to Other Administrative Matters

§ 37.800   Which administrative matters are covered in this subpart?

This subpart addresses “non-systemic” administrative matters that do not impose organization-wide requirements on a participant's financial management, property management, or purchasing system. Because an organization does not have to redesign its systems to accommodate award-to-award variations in these requirements, a TIA that you award may differ from other TIAs in the non-systemic requirements that it specifies for a given participant, based on the circumstances of the particular research project. To eliminate needless administrative complexity, you should handle some non-systemic requirements, such as the payment method, in a uniform way for the agreement as a whole.

Payments

§ 37.805   If I am awarding a TIA, what payment methods may I specify?

Your TIA may provide for:

(a) Reimbursement, as described in 32 CFR 34.12(a)(1), if it is an expenditure-based award.

(b) Advance payments, as described in 32 CFR 34.12(a)(2), subject to the conditions in 32 CFR 34.12(b)(2)(i) through (iii).

(c) Payments based on payable milestones. These are payments made according to a schedule that is based on predetermined measures of technical progress or other payable milestones. This approach relies upon the fact that, as research progresses throughout the term of the agreement, observable activity will be taking place. The recipient is paid upon the accomplishment of the predetermined measure of progress. Fixed-support TIAs must use this payment method and each measure of progress appropriately would be one of the well-defined outcomes that you identify in the agreement (this does not preclude use of an initial advance payment, if there is no alternative to meeting immediate cash needs). There are cash management considerations when this payment method is used as a means of financing for an expenditure-based TIA (see §37.575 and §37.1105).

§ 37.810   What should my TIA's provisions specify for the method and frequency of recipients' payment requests?

The procedure and frequency for payment requests depend upon the payment method, as follows:

(a) For either reimbursements or advance payments, your TIA must allow recipients to submit requests for payment at least monthly. You may authorize the recipients to use the forms or formats described in 32 CFR 34.12(d).

(b) If the payments are based on payable milestones, the recipient will submit a report or other evidence of accomplishment to the program official at the completion of each predetermined activity. The agreement administrator may approve payment to the recipient after receiving validation from the program manager that the milestone was successfully reached.

§ 37.815   May the Government withhold payments?

Your TIA must provide that the administrative agreements officer may withhold payments in the circumstances described in 32 CFR 34.12(g), but not otherwise.

§ 37.820   Must I require a recipient to return interest on advance payments?

If your expenditure-based TIA provides for either advance payments or payable milestones, the agreement must require the recipient to:

(a) Maintain in an interest-bearing account any advance payments or milestone payment amounts received in advance of needs to disburse the funds for program purposes unless:

(1) The recipient receives less than $120,000 in Federal grants, cooperative agreements, and TIAs per year;

(2) The best reasonably available interest-bearing account would not be expected to earn interest in excess of $1,000 per year on the advance or milestone payments; or

(3) The depository would require an average or minimum balance so high that it would not be feasible within the expected Federal and non-Federal cash resources for the project.

(b) Remit annually the interest earned to the administrative agreements officer.

Revision of Budget and Program Plans

§ 37.825   Must I require the recipient to obtain prior approval from the Government for changes in plans?

If it is an expenditure-based award, your agreement must require the recipient to obtain the agreement administrator's prior approval if there is to be a change in plans that results in a need for additional Federal funding (this is unnecessary for a fixed-support TIA because the recipient is responsible for additional costs of achieving the outcomes). Other than that, the program official's substantial involvement in the project should ensure that the Government has advance notice of changes in plans.

§ 37.830   May I let a recipient charge pre-award costs to the agreement?

Pre-award costs, as long as they are otherwise allowable costs of the project, may be charged to an expenditure-based TIA only with the specific approval of the agreements officer. All pre-award costs are incurred at the recipient's risk (i.e., no DoD Component is obligated to reimburse the costs if for any reason the recipient does not receive an award or if the award is less than anticipated and inadequate to cover the costs).

Program Income

§ 37.835   What requirements do I include for program income?

Your TIA should apply the standards of 32 CFR 34.14 for program income that may be generated. Note the need to specify whether the recipient is to have any obligation to the Federal Government with respect to program income generated after the end of the project period (the period, as established in the award document, during which Federal support is provided). Doing so is especially important if the TIA includes a provision for the recipient to return any amounts to the Federal Government (see §37.580).

Intellectual Property

§ 37.840   What general approach should I take in negotiating data and patent rights?

(a) You should confer with program officials and legal counsel to develop an overall strategy for intellectual property that takes into account inventions and data that may result from the project and future needs the Government may have for rights in them. The strategy should take into account any intellectual property the Government is furnishing and any pre-existing proprietary information that the recipient is furnishing, as well as data and inventions that may be generated under the award (recognizing that new data and inventions may be less valuable without pre-existing information). All pre-existing intellectual property, both the Government's and the recipient's, should be marked to give notice of its status.

(b) Because TIAs entail substantial cost sharing by recipients, you must use discretion in negotiating Government rights to data and patentable inventions resulting from research under the agreements. The considerations in §§37.845 through 37.875 are intended to serve as guidelines, within which you necessarily have considerable latitude to negotiate provisions appropriate to a wide variety of circumstances that may arise. Your goal should be a good balance between DoD interests in:

(1) Gaining access to the best technologies for defense needs, including technologies available in the commercial marketplace, and promoting commercialization of technologies resulting from the research. Either of these interests may be impeded if you negotiate excessive rights for the Government. One objective of TIAs is to help incorporate defense requirements into the development of what ultimately will be commercially available technologies, an objective that is best served by reducing barriers to commercial firms' participation in the research. In that way, the commercial technology and industrial base can be a source of readily available, reliable, and affordable components, subsystems, computer software, and other technological products and manufacturing processes for military systems.

(2) Providing adequate protection of the Government's investment, which may be weakened if the Government's rights are inadequate. You should consider whether the Government may require access to data or inventions for Governmental purposes, such as a need to develop defense-unique products or processes that the commercial marketplace likely will not address.

§ 37.845   What data rights should I obtain?

(a) You should seek to obtain what you, with the advice of legal counsel, judge is needed to ensure future Government use of technology that emerges from the research, as long as doing so is consistent with the balance between DoD interests described in §37.840(b). You should consider data in which you wish to obtain license rights and data that you may wish to be delivered; since TIAs are assistance instruments rather than acquisition instruments, however, it is not expected that data would be delivered in most cases. What generally is needed is an irrevocable, world-wide license for the Government to use, modify, reproduce, release, or disclose for Governmental purposes the data that are generated under TIAs (including any data, such as computer software, in which a recipient may obtain a copyright). A Governmental purpose is any activity in which the United States Government participates, but a license for Governmental purposes does not include the right to use, or have or permit others to use, modify, reproduce, release, or disclose data for commercial purposes.

(b) You may negotiate licenses of different scope than described in paragraph (a) of this section when necessary to accomplish program objectives or to protect the Government's interests. Consult with legal counsel before negotiating a license of different scope.

(c) In negotiating data rights, you should consider the rights in background data that are necessary to fully utilize technology that is expected to result from the TIA, in the event the recipient does not commercialize the technology or chooses to protect any invention as a trade secret rather than by a patent. If a recipient intends to protect any invention as a trade secret, you should consult with your intellectual property counsel before deciding what information related to the invention the award should require the recipient to report.

§ 37.850   Should I require recipients to mark data?

To protect the recipient's interests in data, your TIA should require the recipient to mark any particular data that it wishes to protect from disclosure with a legend identifying the data as licensed data subject to use, release, or disclosure restrictions.

§ 37.855   How should I handle protected data?

Prior to releasing or disclosing data marked with a restrictive legend (as described in §37.850) to third parties, you should require those parties to agree in writing that they will:

(a) Use the data only for governmental purposes; and

(b) Not release or disclose the data without the permission of the licensor (i.e., the recipient).

§ 37.860   What rights should I obtain for inventions?

(a) You should negotiate rights in inventions that represent a good balance between the Government's interests (see §37.840(b)) and the recipient's interests. As explained in appendix B to this part:

(1) You have the flexibility to negotiate patent rights provisions that vary from what the Bayh-Dole statute (Chapter 18 of Title 35, U.S.C.) requires in many situations. You have that flexibility because TIAs include not only cooperative agreements, but also assistance transactions other than grants or cooperative agreements.

(2) Your TIA becomes an assistance instrument other than a grant or cooperative agreement if its patent rights provision varies from what Bayh-Dole requires in your situation. However, you need not consider that difference in the type of transaction until the agreement is finalized, and it should not affect the provision you negotiate.

(b) As long as it is consistent with the balance between DoD interests described in §37.840(b) and the recipient's interests, you should seek to obtain for the Government, when an invention is conceived or first actually reduced to practice under a TIA, a nonexclusive, nontransferrable, irrevocable, paid-up license to practice the invention, or to have it practiced, for or on behalf of the United States throughout the world. The license is for Governmental purposes, and does not include the right to practice the invention for commercial purposes.

(c) To provide for the license described in paragraph (b) of this section, your TIA generally would include the patent-rights clause that 37 CFR 401.14 specifies to implement the Bayh-Dole statute's requirements. Note that:

(1) The clause is designed specifically for grants, contracts, and cooperative agreements awarded to small businesses and nonprofit organizations, the types of funding instruments and recipients to which the entire Bayh-Dole statute applies. As explained in appendix B to this part, only two Bayh-Dole requirements (in 35 U.S.C. sections 202(c)(4) and 203) apply to cooperative agreements with other performers, by virtue of an amendment to Bayh-Dole at 35 U.S.C. 210(c).

(2) You may use the same clause, suitably modified, in cooperative agreements with performers other than small businesses and nonprofit organizations. Doing so is consistent with a 1983 Presidential memorandum that calls for giving other performers rights in inventions from Federally supported research that are at least as great as the rights that Bayh-Dole gives to small businesses and nonprofit organizations (see appendix B to this part for details). That Presidential memorandum is incorporated by reference in Executive Order 12591 (52 FR 13414, 3 CFR, 1987 Comp., p. 220), as amended by Executive Order 12618 (52 FR 48661, 3 CFR, 1987 Comp., p. 262).

(3) The clause provides for flow-down of Bayh-Dole patent-rights provisions to subawards with small businesses and nonprofit organizations.

(4) There are provisions in 37 CFR part 401 stating when you must include the clause (37 CFR 401.3) and, in cases when it is required, how you may modify and tailor it (37 CFR 401.5).

(d) You may negotiate Government rights of a different scope than the standard patent-rights provision described in paragraph (c) of this section when necessary to accomplish program objectives and foster the Government's interests. If you do so:

(1) With the help of the program manager and legal counsel, you must decide what best represents a reasonable arrangement considering the circumstances, including past investments, contributions under the current TIA, and potential commercial markets. Taking past investments as an example, you should consider whether the Government or the recipient has contributed more substantially to the prior research and development that provides the foundation for the planned effort. If the predominant past contributor to the particular technology has been:

(i) The Government, then the TIA's patent-rights provision should be at or close to the standard Bayh-Dole provision.

(ii) The recipient, then a less restrictive patent provision may be appropriate, to allow the recipient to benefit more directly from its investments.

(2) You should keep in mind that obtaining a nonexclusive license at the time of award, as described in paragraph (b) of this section, is valuable if the Government later requires access to inventions to enable development of defense-unique products or processes that the commercial marketplace is not addressing. If you do not obtain a license at the time of award, you should consider alternative approaches to ensure access, such as negotiating a priced option for obtaining nonexclusive licenses in the future to inventions that are conceived or reduced to practice under the TIA.

(3) You also may consider whether you want to provide additional flexibility by giving the recipient more time than the standard patent-rights provision does to:

(i) Notify the Government of an invention, from the time the inventor discloses it within the for-profit firm.

(ii) Inform the Government whether it intends to take title to the invention.

(iii) Commercialize the invention, before the Government license rights in the invention become effective.

§ 37.865   Should my patent provision include march-in rights?

Your TIA's patent rights provision should include the Bayh-Dole march-in rights clause at paragraph (j)(1) of 37 CFR 401.14, or an equivalent clause, concerning actions that the Government may take to obtain the right to use subject inventions, if the recipient fails to take effective steps to achieve practical application of the subject inventions within a reasonable time. The march-in provision may be modified to best meet the needs of the program. However, only infrequently should the march-in provision be entirely removed (e.g., you may wish to do so if a recipient is providing most of the funding for a research project, with the Government providing a much smaller share).

§ 37.870   Should I require recipients to mark documents related to inventions?

To protect the recipient's interest in inventions, your TIA should require the recipient to mark documents disclosing inventions it desires to protect by obtaining a patent. The recipient should mark the documents with a legend identifying them as intellectual property subject to public release or public disclosure restrictions, as provided in 35 U.S.C. 205.

§ 37.875   Should my TIA include a provision concerning foreign access to technology?

(a) Consistent with the objective of enhancing the national security by increasing DoD reliance on the U.S. commercial technology and industrial bases, you must include a provision in the TIA that addresses foreign access to technology developed under the TIA.

(b) The provision must provide, as a minimum, that any transfer of the:

(1) Technology must be consistent with the U.S. export laws, regulations and policies (e.g., the International Traffic in Arms Regulation at chapter I, subchapter M, title 22 of the CFR (22 CFR parts 120 through 130), the DoD Industrial Security Regulation in DoD 5220.22–R,6 and the Department of Commerce Export Regulation at chapter VII, subchapter C, title 15 of the CFR (15 CFR parts 730 through 774), as applicable.

6 Electronic copies may be obtained at the Washington Headquarters Services Internet site http://www.dtic.mil/whs/directives. Paper copies may be obtained, at cost, from the National Technical Information Service, 5285 Port Royal Road, Springfield, VA 22161.

(2) Exclusive right to use or sell the technology in the United States must, unless the Government grants a waiver, require that products embodying the technology or produced through the use of the technology will be manufactured substantially in the United States. The provision may further provide that:

(i) In individual cases, the Government may waive the requirement of substantial manufacture in the United States upon a showing by the recipient that reasonable but unsuccessful efforts have been made to transfer the technology under similar terms to those likely to manufacture substantially in the United States or that under the circumstances domestic manufacture is not commercially feasible.

(ii) In those cases, the DoD Component may require a refund to the Government of some or all the funds paid under the TIA for the development of the transferred technology.

(c) You may, but are not required to, seek to negotiate a domestic manufacture condition for transfers of nonexclusive rights to use or sell the technology in the United States, to parallel the one described for exclusive licenses in paragraph (b)(2) of this section, if you judge that nonexclusive licenses for foreign manufacture could effectively preclude the establishment of domestic sources of the technology for defense purposes.

Financial and Programmatic Reporting

§ 37.880   What requirements must I include for periodic reports on program and business status?

Your TIA must include either:

(a) The requirements in 32 CFR 32.51 and 32.52 for status reports on programmatic performance and, if it is an expenditure-based award, on financial performance; or

(b) Alternative requirements that, as a minimum, include periodic reports addressing program and, if it is an expenditure-based award, business status. You must require submission of the reports at least annually, and you may require submission as frequently as quarterly (this does not preclude a recipient from electing to submit more frequently than quarterly the financial information that is required to process payment requests if the award is an expenditure-based TIA that uses reimbursement or advance payments under §37.810(a)). The requirements for the content of the reports are as follows:

(1) The program portions of the reports must address progress toward achieving program performance goals, including current issues, problems, or developments.

(2) The business portions of the reports, applicable only to expenditure-based awards, must provide summarized details on the status of resources (federal funds and non-federal cost sharing), including an accounting of expenditures for the period covered by the report. The report should compare the resource status with any payment and expenditure schedules or plans provided in the original award; explain any major deviations from those schedules; and discuss actions that will be taken to address the deviations. You may require a recipient to separately identify in these reports the expenditures for each participant in a consortium and for each programmatic milestone or task, if you, after consulting with the program official, judge that those additional details are needed for good stewardship.

§ 37.885   May I require updated program plans?

In addition to reports on progress to date, your TIA may include a provision requiring the recipient to annually prepare updated technical plans for the future conduct of the research effort. If your TIA does include a requirement for annual program plans, you also must require the recipient to submit the annual program plans to the agreements officer responsible for administering the TIA.

§ 37.890   Must I require a final performance report?

You need not require a final performance report that addresses all major accomplishments under the TIA. If you do not do so, however, there must be an alternative that satisfies the requirement in DoD Instruction 3200.147 to document all DoD Science and Technology efforts and disseminate the results through the Defense Technical Information Center (DTIC). An example of an alternative would be periodic reports throughout the performance of the research that collectively cover the entire project.

7 See footnote 6 to §37.875(b)(1).

§ 37.895   How is the final performance report to be sent to the Defense Technical Information Center?

(a) Whether your TIA requires a final performance report or uses an alternative means under §37.890,8 you may include an award term or condition or otherwise instruct the recipient to submit the documentation, electronically if available, either:

8 Additional information on electronic submission to the DTIC can be found online, currently at http://www.dtic.mil/dtic/submitting/elec_subm.php.

(1) Directly to the DTIC; or

(2) To the office that is administering the award (for subsequent transmission to the DTIC).

(b) If you specify that the recipient is to submit the report directly to the DTIC, you also:

(1) Must instruct the recipient to include a fully completed Standard Form 298, “Report Documentation Page,” with each document, so that the DTIC can recognize the document as being related to the particular award and properly record its receipt; and

(2) Should advise the recipient to provide a copy of the completed Standard Form 298 to the agreements officer responsible for administering the TIA.

§ 37.900   May I tell a participant that information in financial and programmatic reports will not be publicly disclosed?

You may tell a participant that:

(a) We may exempt from disclosure under the Freedom of Information Act (FOIA) a trade secret or commercial and financial information that a participant provides after the award, if the information is privileged or confidential information. The DoD Component that receives the FOIA request will review the information in accordance with DoD procedures at 32 CFR 286.23(h) (and any DoD Component supplementary procedures) to determine whether it is privileged or confidential information under the FOIA exemption at 5 U.S.C. 552(b)(4), as implemented by the DoD at 32 CFR 286.12(d).

(b) If the participant also provides information in the course of a competition prior to award, there is a statutory exemption for five years from FOIA disclosure requirements for certain types of information submitted at that time (see §37.420).

§ 37.905   Must I make receipt of the final performance report a condition for final payment?

If a final report is required, your TIA should make receipt of the report a condition for final payment. If the payments are based on payable milestones, the submission and acceptance of the final report by the Government representative will be incorporated as an event that is a prerequisite for one of the payable milestones.

Records Retention and Access Requirements

§ 37.910   How long must I require participants to keep records related to the TIA?

Your TIA must require participants to keep records related to the TIA (for which the agreement provides Government access under §37.915) for a period of three years after submission of the final financial status report for an expenditure-based TIA or final programmatic status report for a fixed-support TIA, with the following exceptions:

(a) The participant must keep records longer than three years after submission of the final financial status report if the records relate to an audit, claim, or dispute that begins but does not reach its conclusion within the 3-year period. In that case, the participant must keep the records until the matter is resolved and final action taken.

(b) Records for any real property or equipment acquired with project funds under the TIA must be kept for three years after final disposition.

§ 37.915   What requirement for access to a for-profit participant's records do I include in a TIA?

(a) If a for-profit participant currently grants access to its records to the DCAA or other Federal Government auditors, your TIA must include for that participant the standard access-to-records requirements at 32 CFR 34.42(e). If the agreement is a fixed-support TIA, the language in 32 CFR 34.42(e) may be modified to provide access to records concerning the recipient's technical performance, without requiring access to the recipient's financial or other records. Note that any need to address access to technical records in this way is in addition to, not in lieu of, the need to address rights in data (see §37.845).

(b) For other for-profit participants that do not currently give the Federal Government direct access to their records and are not willing to grant full access to records pertinent to the award, there is no set requirement to include a provision in your TIA for Government access to records. If the audit provision of an expenditure-based TIA gives an IPA access to the recipient's financial records for audit purposes, the Federal Government must have access to the IPA's reports and working papers and you need not include a provision requiring direct Government access to the recipient's financial records. For both fixed-support and expenditure-based TIAs, you may wish to negotiate Government access to recipient records concerning technical performance. Should you negotiate a provision giving access only to specific Government officials (e.g., the agreements officer), rather than a provision giving Government access generally, it is important to let participants know that the OIG, DoD, has a statutory right of access to records and other materials to which other DoD Component officials have access.

§ 37.920   What requirement for access to a nonprofit participant's records do I include in a TIA?

Your TIA must include for any nonprofit participant the standard access-to-records requirement at:

(a) 32 CFR 33.42(e), for a participant that is a State or local governmental organization.

(b) 32 CFR 32.53(e), for a participant that is a nonprofit organization. The same requirement applies to any nonprofit GOCO or FFRDC, even though nonprofit GOCOs and FFRDCs are exempted from the definition of “recipient” in 32 CFR part 32.

Termination and Enforcement

§ 37.925   What requirements do I include for termination and enforcement?

Your TIA must apply the standards of 32 CFR 34.51 for termination, 32 CFR 34.52 for enforcement, and your organization's procedures implementing 32 CFR 22.815 for disputes and appeals.

Browse Previous |  Browse Next






















chanrobles.com


ChanRobles Legal Resources:

ChanRobles On-Line Bar Review

ChanRobles Internet Bar Review : www.chanroblesbar.com

ChanRobles MCLE On-line

ChanRobles Lawnet Inc. - ChanRobles MCLE On-line : www.chanroblesmcleonline.com