33 C.F.R. § 154.1135 Response plan development and evaluation criteria.
Title 33 - Navigation and Navigable Waters
The following response times must be used in determining the on scene arrival time in Prince William Sound for the response resources required by §154.1045:
Title 33: Navigation and Navigable Waters
PART 154—FACILITIES TRANSFERRING OIL OR HAZARDOUS MATERIAL IN BULK
Subpart G—Additional Response Plan Requirements for a Trans-Alaska Pipeline Authorization Act (TAPAA) Facility Operating in Prince William Sound, Alaska
§ 154.1135 Response plan development and evaluation criteria.
------------------------------------------------------------------------ Tier 1 Tier 2 tier 3 (hrs.) (hrs.) (hrs.)------------------------------------------------------------------------Prince William Sound Area.................... 12 24 36------------------------------------------------------------------------